4.CL3- Procurment & Tendering Flashcards
What is procurement?
Procurement is a process of acquiring good, services or works from an external source.
What are the factors affecting choosing procurement route?
Cost
Quality
Time
Risk
What are the procurement routes?
- Traditional
- Design and Build
- Management Contract
- Construction Management
What is Traditional Procurement
• Client appoints consultants to design the project in detail and prepare tender docs
• Contractors submit tenders on a single stage competitive basis
• When to use:
Design is fully complete
Client wishes to maintain control over design and spec
Cost certainty
Time certainty is not a priority
• RIAI, PW-CF1 Building Works Designed by the Employer
What is Design & Build
• Client appoints contractor to design construct the works
• Client issues Employers Requirement Documents (ERD’s) which the contractor use to formulate their price. Very important for this to be a complete document as it gives contractor clear scope as to what to price
• Client may wish to appoint independent advisors to review contractor’s proposals, administer the contract and monitor works on site.
• When to use:
need to make an early start on site – can overlap design and construction
client wishes to minimise their risk – no responsibility for design
technically complex projects which can benefit from the contractor’s expertise
employer does not want to retain full control over the design development
• RIAI amended, PW-CF2 Building Works Designed by the Contractor
What is Management Contracting
• Works are constructed by a number of difference contractors who are contracted to a management contractor
• Management contractor is appointed by the client early in the design process to use their experience to improve cost and buildability of proposals
• Management contractor is paid a fee to manage the building of a project on behalf of the client
• Sub-contract packages prepared for tender by the QS with input from MC
• Sub-contractors are selected and interviewed jointly by the DT and MC
• When to use:
Large scale complex projects requiring early start on site
Work needs to be started before design complete allowing overlaps between tendering and design
Employer requires ECI to facilitate buildability and cost efficiency based on their expertise
Client wants to maintain control of design while there is design flexibility throughout the construction process.
Client wants to move risks of procurement and delivery to management contractor.
• PWC-CF10 Public Works for ECI (note projects must exceed €100 million).
• Specifically drafted RIAI blue forms, JCT Management Contract Agreements, NEC Option F Management Constract
What is Construction Management
• Construction management is where the works are constructed by a number of different trade contractors contracted directly to the client but managed by a construction manager (CM).
• The expertise of the CM is used to coordinate the contracts and acts as a consultant to the client.
• The CM has no contractual links to the trade contractor or design team.
• CM is appointed early in the design process to improve buildability and design.
• When to use:
Same reasons as MC.
Only suitable for very experienced clients as they are required to place and administer trade contracts.
• PWC-CF10 Public Works for ECI (note projects must exceed €100 million).
• Specifically drafted RIAI blue forms or JCT Construction Management Agreements
What is tendering?
The is a method of obtaining the resources to carry out required works.