1. CL3- Commercial management of Construction Flashcards

1
Q

What types of estimates are there?

A

a) Budget .
b) Cost estimate – point in time “this is what I think the project will cost”.
c) Cost plan – cost plan is live.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a feasibility estimate?

A

• A high level exercise to assess whether a project is financially viable and to set an outline budget for the scheme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What information do you need to be able to carry out a feasibility estimate?

A
  • Type of building (function)
  • New build or extension
  • Location
  • Size
  • Indication of quality
  • Site visit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a cost estimate?

A

• A forecast of the possible cost of a building based on historical data.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the principal components of a cost plan?

A
  • Construction cost.
  • Preliminaries.
  • Contractor’s OH&P.
  • Contingency.
  • Inflation.
  • Assumptions – programme.
  • Exclusions and assumptions.
  • Area Schedule.
  • Basis of Estimate – drawings / specifications list.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a development budget

A

The client’s total budget for the entire project – which is useful to deem whether the project is viable and profitable:
- Construction cost

  • Land and property acquisition costs
  • Approval fees
  • Planning costs – S106 and CIL
  • Financing costs
  • Site investigations
  • FFE
  • Moving staff
  • Insurance
  • Consultant fees
  • Inflation
  • Contingency
  • VAT
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you proceed if the cost plan exceed s the project budget?

A

I would analyse the costs to assess the source of the increase and identify whether any element of work is abnormally high against the order of cost estimate .
When the reason for the overspend is identified I would then look to propose value engineering options to my client and design team to bring the forecast back in line with the project budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a functional unit?

A
  • The ‘factors which express the intended use of the building better than any other’.
  • E.g. number of bedrooms in a hotel, number of beds in a hospital.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a cost plan?

A

•Cost plan is a detailed plan of costs for the works

The cost plan presents the estimated cost of the development into an elemental or functional format.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is contingency?

A

• A sum included in the estimate to cover unknown expenses or unmitigated risks during the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How is contingency assessed?

A
  • The amount included should reflect the risks and unknowns specific to the project.
  • During early estimates when little information is available it is common to include a higher.
  • Design risk, construction risk.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How would you establish a project budget?

A

• Comparison with similar projects.
• Assessment of funds available.
• Cost plan handover and setting up of the construction budget.
o Amend and revise costs based on changes from cost plan stage to construction stage
o Establish fees & contributions
o Establish build costs
Quantify detailed design.
Benchmark rates from similar projects.
 Market rates and quotes.
Schedule of prelims based on resources and construction programme.

o Set contingency for design development and unknowns throughout construction phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the purpose of a cash flow?

A
  • Provides client / finance with forecast of likely expenditure, to allow finance to be raised.
  • Provides comparison to actual certification, aids monitoring of programme etc
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How would you create a cashflow forecast?

A
  • Apply established project construction budget to the scheduled programme of works. This includes prelims, fees & contributions, BoQ values and contingency.
  • Exercise should result in an S curve.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the Purpose of Cost Reporting

A
  • The purpose of cost reporting is to inform the likely outturn cost of the construction project.
  • To report against budgeted values and act as a working cost check on the project budget.
  • To give the Client an understanding of any savings or additional monies required.
  • To report on contract progress against pre-contract predictions.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What elements do you report against in your cashflow

A
Elements covered:
•Fees & Contributions
  o	Post planning fees
  o	Hombond fees
  o	Financial contributions
  o	Utility Fees
•Build Costs
  o	Site development
  o	Apartments
  o	Prelims
  o	Abnormals
•Contingency

Contains:
• original budget set at cost plan handover.
• projected final account figures all elements.
• Compares variances between PFA and budget.
• Compares variances between previous pfa and current PFA.

17
Q

What is value engineering?

A

Value engineering is an exercise that involves seeking the most cost effective solutions in design and subsequent implementation of that solution into the design for project delivery.nce or delivery.

18
Q

What happens throughout the VE process?

A
  • Design team / Project team brought together – QS, Arch, Eng, Contractor etc.
  • Pool expertise to come up with best solution from a design, buildability and cost efficient perspective.
  • Not a cost cutting exercise as this leads to reduced quality and value.
19
Q

What is Loss and Expense

A

Contractor claims for direct loss/or expense as a result of the progress of works being affected by relevant events which the client is responsible for such as:

  • Failure to give contractor possession of the site – RIAI TIME & COST
  • Delays in receiving instructions – RIAI TIME & COST
  • Instructed variations – RIAI TIME & COST
  • Force Majeure – RIAI TIME ONLY
  • Exceptionally inclement weather – RIAI TIME ONLY
20
Q

How would you ascertain value of L&E?

A

Depends on the relevant event and what way the contract is set up?
• Is it time? Is it time and cost?
• Does the L&E arise from:
• Legislative enactments
• Late possession
• Delays in receiving instruction
• Force Majeure

21
Q

How Would you value a variation

A

I. Existing similar BoQ rates
II. Pro-rata of existing similar BoQ rates
III. Similar market rates in the locality
IV. Dayworks
V. Rate build up from first principles

22
Q

What is contingency?

A

• A sum included in the estimate to cover unknown expenses or unmitigated risks during the project.

23
Q

How is contingency assessed?

A

•- Contingencies are downside risk estimates that make allowance for the unknown risks associated with a project.

  • Sometimes based on a percentage
  • Adverse weather, unforeseen circumstances, disputes, supplier failure, variations, unexpected site conditions
24
Q

What is risk defined as?

A

• An uncertain event that may effect on the achievement of the project objectives measured in terms of likelihood (probability) and consequence (impact).

25
Q

Why is risk management needed in construction?

A
  • Projects are typically complex, all have time, cost and quality targets which must be met.
  • Risk is present in all projects and surveyors are routinely involved in making decisions which have a major impact on risk.
  • Risk management cannot eliminate risk, but techniques can be used to reduce the impact of events that may cause failure to reach the desired targets.
26
Q

What are the stages of Risk Management?

A
  • IDENTIFY
  • RESPOND
  • ANALYSE/ ASSESS
  • MONITOR AND CONTROL
27
Q

Can you give me some examples of risk in a construction project?

A
  • External risks: economic, legal, political
  • Financial risks: exchange rate, funding
  • Site risks: Restricted, occupied site, planning difficulties, access, environmental
  • Client risks: lack of experience, multi-headed client, likelihood of post contract changes.
  • Design risks: inappropriate consultant team, poor brief, incomplete design, co-ordination.
  • Selection of appropriate contractor: inadequate selection process
  • Construction and delivery risks: weather
28
Q

How do you report/ monitor risks?

A
  • Using a risk register: Risks are logged, tracked through the life of the project.
  • Item: Threats/ Opportunities likelihood/ impact. Placed in a category e.g. client control, share.
  • Needs regularly updating
29
Q

What are the benefits of risk management?

A
  • Increased confidence in achieving project objectives and success
  • Surprises reduced cost/ time overruns
  • Team understands and recognises the use and composition of contingencies
  • Enable decision making to be made on an assessment of known variables available
  • Risk management workshops can facilitate team development and encourage communication