Always assume the Skyway is energized when?
24 hours a day 7 days a week
When do operations on the Skyway commence
not until the Skyway has been de-energized and the IC has been notified
How would you verify that the power has been disconnected?
by using the Tig-Tracer
Where might ground ladders not be able to reach?
San Marco area. Elevations exceed 52 feet
Where is power supplied to the breakers?
transformers outside the stations
Where are the breakers located?
inside the equipment rooms
Where are the PDP’s located?
at each passenger station and switch.
how can power be shut down at the Control Center?
Power can be shut down in sections or all at once.
must be all at once until the location of the incident can be verified
Where are the blue light stations located?
diagonally to each other, BUT NOT VISIBLE from each other.
BLUE LIGHT stations must be activated on?
BOTH sides of the emergency as well as the station involved.
BLUE LIGHT STATIONS -
If a larger area needs to be de-energized?
the BLUE LIGHT station at the next passenger loading station needs to be activated.
Where is the Y-junction located?
Bay and Jefferson streets.
Why is the Y-junction area still a potential crushing hazard even after the power is shut down?
it has sections of the track that are hydraulically operated and electrically actuated.
Where is the Skyway Express Control Center building located/
725 Leila Street.
Where is the control room located?
2nd floor of the Skyway Control Center
There will be no operator on-duty at the Skyway Control Center from
2330 Friday night until 0400 Monday morning.