4.2. Production Engineering Flashcards
1
Q
Some questions regarding TAKT.
- How do i deal with (short term) fluctuations in demand in takted work systems?
- How can seasonality be represented?
- How do i deal with different sickness rates?
- What can be done if customer demand changes in the long run?
A
- dont change speed of line everytime there is change in demand -> you DO change the gross or net working time (e.g. demand + 10% = increasing working time +10%)
- going in stock production before; change gross working time
- rented labor; need to make sure every spot is covered; otherwise go for U-cell system
- need to re-calculate TAKT time
2
Q
Whats a routing?
A
- the basis for capacity planning and throughput scheduling of orders
- structures production sequence
- very standardized in mass production
3
Q
Kanban is one of the decentralized control principles.
Yes or No?
A
Yes!
Centralized = central authority like production manager makes decisions about what to produced.
Decentralized= Decisions made more locally, often at the level of individual workstations, production lines or teams. Allo each part of production to act more independently.