3.1 Inventory Management Flashcards
What is the Sawtooth model? What does it do?
Some help:
Safety stock?
RLT?
AS?
ROP?
- helps in material planning based on calculating the reorder point (ROP)
- inventory is used over time until ROP, then we order a certain quantity
- ROP = (planned) demand per day * replenishment time in days + safety stock
- order interval: moment you order until next order
- replenishment lead time: order until delivered
What what the different order mechanisms?
1.
2.
3.
4.
- fix Q (quantity) + flexible S (stock) = reorder point method (order fixed Q when min stock is reached)
- variable order Q + flexible S = order at min stock level; fill up to predefined stock level
- fix Q + fix S = very rigid; order fix Q according to time schedule
- variable S, fix Q = order on schedule; fill up to predefined stock level
What causes fluctuations of the stock?
1.
2.
3.
- change in demand rate: faster fall, faster under safety stock
- delivery time takes too long; after delivery then we dont reach max inventory
- demand and delivery same, but poor quality
Tell to the following Safety Stock levels whether they are sufficient for a Re order point of 5,000 pcs, a consumption of 300 pcs per day, and a RLT of 12 days.
- SS = 3,600
- SS= 1,200
- SS= 3,150
12*300 = 3,600 consumption during RLT
5,000-3,600 = 1,400 safey stock
- not enough
- enough
- not enough
What are drivers that determine the Lot sizes for the following roles:
- Purchasing Manager
- Warehouse Manager
- Quality Manager
- scale effects due to larger Quantity (high)
- transportation costs, lower when Q high (high)
- expediting and postponing of orders (high)
- capital bound is smaller when small POs (purchase order, low)
- packing Qs, due to transportation securing instructions (high)
- inventory costs, high when high PO lot sizes (does NOT affect handling) (low)
- obsolence (veralterung) of stock due to high PO, (low)
- process costs lower when high PO, e.g. inspections (high)Det
Determination of Lot Sizes
- Expediting of Orders
- Postponement of Orders
- needing more, earlier than agreed
- e.g. when you need later than agreed; try keeping PO low and lot size HIGH
Delivery services measures….
Delivery service level consists of…
1.
2.
…. the punctuality of deliveries
- readiness for delivery: ability to deliver immediately from stock (only for make-to-stock or retail)
- delivery reliability (DR): ability to meet deadlines including make-to-order, engineer to order etc
DR: qty of products, delivered at the date which had been confirmed first / qty of confirmed products
- Determination of the delivery service is a balance between…
- The goal here is to minimize…
- shortfall costs and inventory costs
- the sum of shortfall costs and inventory/storage costs
Shortfall costs….
1.
2.
3.
- correspond to either the contribution margin or the cost of special measures
- option 1: accept the loss of delivery service and the costs that result from it (SFC= Contribution margin * QTY); also in long term due to lost reputation
- option 2: delivery service constant due to contermeasures (SFC= costs for e.g. special transport + surcharge for higher procurement DMC (direct material costs) + additional administrative expenditure)
- Purchase to Pay (P2P) is often used synonymously with…
- Its components are… (6)
- these processes are based upon…
- operational purchasing
- Solicitation of quotations -> order -> open order mngmt -> goods receipt -> invoice receival & verification -> payment
- the strategic sourcing (supplier mngmnt & procurement concepts
- The P2P purchase is important for….
- And its objectives are…
- Its challenges are…. (5)
- material availability and cash flow
- provision of required material according to planned (replenishment-) time, agreed quality and agreed amount
- sometimes long thorughput time of process; many critical tasks / activities; involvement of many departments of a company; deviations frequently followed by severe consequences; important for the cash flow of a company bc you have payment targets
P2P process | What are….
- solicitation of quotations?
- placement of order?
- open order management?
- transmission of RFQ (requests for quotations) to selected suppliers, which will be assed and the best ones chosen
- transmission of order with specification to agreed Quantities and schedules, based on quotation or contract (transmissioned via mail, IT systems, platforms)
- revision of order ; check for errors and then accept; revision of milestones, determination of corrective actions in case of deviations (first check supplier side then itnernally)
P2P process | What is…
- goods receipt
- invoice receival & verification
- payment
- goods arrive; are inspected according to criteria; release or blocking of goods; booking what has been delivered, need to do validation first(; transfer to stock or receiving department)
- receive invoice; check, release invoice for payment
- payment according to terms; if applicablem utilize cash discounts
What are the different possiblities of E procurement?
1.
2.
3.
- sell-side / supplier systems, which are provided by supplier or seller (eg amazon)
- buy-side / procurement systems, which are provided by purchasing company (eg dektop purchasing systems)
- market place, provided by third party (eg amazon market place)
Whats a tender? what are the different options here?
1.
2.
3.
4.
- ausschreibung
- can be made by contracting authorities (public or restricted) or private enterprises
- public tender: award procedure; against corruption and everyone has access; generally needs to make public
- restricted tender: only with special reason and for limited companies Wh(eg only big companies have the capabilites /capacity)