4 - Create Work Center Flashcards

TCODE: CR01 To Learn: How to create a new Work Center Business Scenario: ---------------------------- A new automatic steel cutting saw machine has arrived at the plant. In order to allocate work to this machine, it needs to be created as a Work Center. You have been asked to create the Work Center for this new steel saw.

1
Q

Production Work Center Activities are valued by which of the following?

a) - US Dollars
b) - Time
c) - Charge rates

A

c) - Charge rates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A Production Work Center always has to be tried to which of the following?

a) - Company Code
b) - Material Number
c) - Cost Center
d) - Plant

A

d) - Plant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A Production Work Center has ——————————
Capacity.

a) - unlimited
b) - specific
c) - either unlimited or specific

A

b) - specific

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which of the following are examples of Work Centers? (Please select all that apply)

a) - Machinery
b) - Production Line
c) - Hydraulic Press

A

a) - Machinery
b) - Production Line
c) - Hydraulic Press

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A Work Center is considered to be…………………………….:

a) - an Organisational Unit
b) - a Labor Unit
c) - a Machine Unit

A

a) - an Organisational Unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

People can be setup as Work Center

a) - incorrect, a Work Center HAS TO BE a place.
b) - incorrect, a Work Center MUST be a machine or job.
c) - Correct, a person could be a Work Center.

A

c) - Correct, a person could be a Work Center.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly