Q

List the trap selection criteria for the application?

1) condensate capacity, under start up
2) condensate capacity, under normal operating
3) condensate temperature the trap will have to handle
4) steam header temperature
5) pressure differential across the trap
6) the location of the trap

A) 1,3,4,5,6
B) 1,2,3,4,5,6
C) 1,2,3,5,6
D) 1,2,3,4
E) 5,6
A

B) 1,2,3,4,5,6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Find the warm up load in kg/h in warming up 50 m of203.2 mm, schedule 40 steel pipe to a working pressure of 1737 kPa in a warm up time of 20 minutes. Initial temperature of the pipe is 20 degrees C table 1 lists the dimensions and mass per meter of different sizes of steel pipe with varying wall thickness

A) 500 kg
B) 102.89 kg
C) 58 kg
D) 1002.89 kg

A

B) 102.89 kg

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In order to determine the correct size of the trap for an application, it is necessary to calculate the condensate load to be removed by the trap, per hour

A) true
B) false

A

A) true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In order to accomplish this warmup in 20 minutes, the condensate rate /h would be:

A) 308.67 kg/h
B) 125 kg/h
C) 254 kg/h
D) 132 kg/h

A

A) 308.67 kg/h

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If a group of traps drain into a common return header, a check valve should be installed between the trap and the supply header

A) true
B) false

A

B) false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

To have a single trap for two units is permitted, as long as the trap capacity is not exceeded

A) true
B) false

A

B) false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The most positive method to test a trap to ensure it is working is to touch the body of the trap

A) true
B) false

A

B) false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Describe three tasks done on a yearly trap inspection
A) the trap body and operating parts should be examined for corrosion, erosion, mechanical wear, etc.
B) all internal parts should be cleaned and worn valves, seats, levers, etc., should be replaced, as should cracked buckets, floats or bellows
C) check trap housing temperature
D) all gasket seating surfaces should be thoroughly cleaned and new gaskets used on reassembly

A) a,b,c,d
B) a,b
C) a,b,d
D) d

A

C) a,b,d

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The proper design of the trap and condensate return system is critical in preventing water ham,era in a condensate system

A) true
B) false

A

A) true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

If a lift is used, then the most common type of trap used is the thermostatic trap

A) true
B) false

A

B) false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In some systems where the temperature from e condensate stream is _____ than ______, a small _______ of s used to_____ the cooler condensate

A) much cooler, another stream, steam heat exchanger, heat up
B) hotter, water, steam injection, change
C) colder, steam, temperature gauge, measure
D) smaller, the other, time count, blend

A

A) much cooler, another stream, steam heat exchanger, heat up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What checks will be made to ensure a line is completely drained of condensate?
A) make sure that the lord new is completely blocked in at both ends
B) slowly open each low point drain on steam line. Be sure the drain lines are free and clear of any blockage
C) open downstream flange
D) check that each trap is in service
E) ensure the condensate has been drained from the pressurized side of the steam supply valve

A) a,b,d,e
B) a,b,c,d,e
C) a,b,e
D) a,b

A

A) a,b,d,e

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

List three purposes of insulation:

1) retains the heat of the hot lines
2) protects the metal surfaces from rust
3) prevents the temperature inside the power plant building from becoming uncomfortably high
4) insulating of hot pipelines will prevent injury to personnel due to contact with the bare surfaces of the pipe

A) 2,3,4
B) 1,2,3
C) 1,3,4
D) 1,2,4

A

C) 1,3,4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The coefficient of thermal conductivity of a material is a measure of the amount of heat that will be transmitted through this material. Therefore, the higher the value of thermal conductivity for a material, the better will be its insulating ability

A) true
B) false

A

B) false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What type of insulation will most likely be used for HP steam piping?

A) fibreglass
B) cloth
C) calcium silicate
D) refractory fibre

A

C) calcium silicate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Piping insulation is normally fabricated in half cylindrical sections for fitting over the pipe. It is held together by _____ or _____, and then _____ with _____ _____, ____ or galvanized steel

A) glue, tape, covered, fabric, sheeting
B) metal wire, bands, covered, sheet metal, aluminum
C) gravity, weight, pasted, plaster, sheeting
D) friction, tightness, closed, paint, tar

A

B) metal wire, bands, covered, sheet metal, aluminum

17
Q

The environment determines whether to use aluminum or stainless steel cladding. If metal cladding is used in a chemical installation where there are caustic lines, the insulation is covered or wrapped with stainless steel. This is done to prevent damage the the covering in the event of a leak or spill

A) true
B) false

A

A) true

18
Q

Insulating blankets are used in various applications. They are difficult to install and remove for maintenance. They are very convenient for use with expansion joints, valves, steam traps, and other odd shaped vessels, and they can be used in high temperature applications

A) true
B) false

A

B) false