3.3.4 Critical Path Analysis (2/2) Flashcards

1
Q

Network diagram

A

A chart showing the order of tasks involved in completing a project, containing information about the times taken to complete the tasks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Critical path

A

Main tasks

-The tasks involved in a project which, if delayed, could delay the whole project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do you know what the critical path is

A

The EST & LFT are the same number always

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Nodes are in what shape

A

Circler

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Left number in node meaning

A

Node/Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Earliest start time (EST)

Where is it positioned on the node?

A

How soon a task in a project can begin.

It is influenced by the length of time taken by tasks which must be completed before it can begin.

TOP RIGHT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Latest finish time

where is it positioned on the node?

A

The latest time a task in a project can finish

BOTTOM RIGHT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EST & LFT are always the same at which nodes

A

First nodes (0,0)
And
Last nodes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

On the lines/Arrows what is on top and below

A

On top - task/activity

Below - time/duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EST is always calculated from where to where

A

From left to right

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

LFT is always calculated from where to where

A

right to right

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Total float

A

the time by which a task can be delayed without affecting the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Total float calculation

A

LFT of activity - EST of activity - Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Free float

A

the time by which a task can be delayed without affecting the following task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

free float calculation

A

EST start of next task - EST start of this task - Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly