3.3.4 Critical Path Analysis Flashcards
1
Q
What is critical path analysis
A
a project management tool that uses network analysis to plan complex and time-sensitive projects
Shown through a visual model
2
Q
What are the key elements in a CPA diagram? 3
A
- A list of all the activities required to complete the project
- The time (duration) that each activity will take to complete
- How each project activity depends on others
3
Q
What does critical path analysis show?
A
- The order activities need to be completed in
- The longest path to complete the project
- The earliest and latest that each project activity can start and finish without delaying completion of the project as a whole
- Activities that can be carried out simultaneously
- The critical project activities which, if delayed will cause the project as a whole to over-run
- Activities where delay can occur without delaying the project as a whole
- The shortest time possible to complete the project
4
Q
A