3.3.4 Critical Path Analysis Flashcards
Define critical path analysis
Used to find the most efficient and cost-effective way of doing a complex project
What are the circles on the network called?
Nodes
What do nodes show?
Where one activity stops and another one begins
What do the numbers in a node show?
The number of the node
EST - earliest start time of the next activity
LFT - latest finishing time of the activity
How is EST worked out?
Add the duration of the previous activity to its EST.
What is the EST of the first activity?
Always 0
How is LFT worked out?
Calculated by working backwards from the final node.
The LFT of the final node is the same as it’s EST.
To work out the LFT of the node before, you minus the duration of the next activity from its LFT.
Define float time
The length of time you can delay an activity without delaying the completion of the project
How is float time calculated?
LFT - duration - EST
Advantages of using CPA
- Stakeholders can see the total time frame for the project to be completed
- Parallel activities can be scheduled to save time
- Useful to decide when resources should be delivered
Limitations of using CPA
- Based on estimates so not always accurate
- Drawing up a diagram is time consuming