3.3.4 Critical Path Analysis Flashcards

1
Q

Define critical path analysis

A

Used to find the most efficient and cost-effective way of doing a complex project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the circles on the network called?

A

Nodes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What do nodes show?

A

Where one activity stops and another one begins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What do the numbers in a node show?

A

The number of the node
EST - earliest start time of the next activity
LFT - latest finishing time of the activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How is EST worked out?

A

Add the duration of the previous activity to its EST.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the EST of the first activity?

A

Always 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is LFT worked out?

A

Calculated by working backwards from the final node.
The LFT of the final node is the same as it’s EST.
To work out the LFT of the node before, you minus the duration of the next activity from its LFT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define float time

A

The length of time you can delay an activity without delaying the completion of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is float time calculated?

A

LFT - duration - EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Advantages of using CPA

A

- Stakeholders can see the total time frame for the project to be completed
- Parallel activities can be scheduled to save time
- Useful to decide when resources should be delivered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Limitations of using CPA

A

- Based on estimates so not always accurate
- Drawing up a diagram is time consuming

How well did you know this?
1
Not at all
2
3
4
5
Perfectly