CPA
management tool that helps bs to identify how long a project will take and what the critical tasks in the project are.
nature and purpose of CPA
calculates minimum time needed to complete a project
identifies delays
aids w planning, organisation and resource management
critical path
determines the shortest time possible to complete the project- all the ones where the no on top and bottom are same. quickest route
EST
first node always 0-0.
do the 0 + the next duration= EST
if two pick the largest answer
work left to right, this no goes on top
LFT
last node always same no.
do the last LFT minus the next duration= LFT
if two pick largest one out of the two answers
work right to left, this no. goes on bottom
pros of CPA
float formula
LFT (of one your calculating)-EST(of last one)-duration
cons of CPA