3.2 Development Issues Flashcards
What will L likely opt to use in A4L to ensure T completes on time, or A4L terminates if fails to do so
Notice to complete procedure - making time of the essence
Why allow for long-stop date for delays
If issue does not resolve itself, parties should be able to walk away
If defect in L’s retained premises, who is liable and who will pay
L liable, but will recover through service charge
If defect inside T’s premises, who is liable and under what
T under repairing Os
Who drafts A4L
L’s S
What method is commonly used for Completion Statement
Surveyor’s method
Why disregard T’s works at RR
Artificially inflates hypothetical lease - only benefits L
If T carried out works but L requires reinstatement under A4L, what should you ensure it says
Such as L may reasonably require
If T in strong position, what could you negotiate for in terms of T’s A’s defect notice
Require L’s A to act reasonably in considering DN, and take reasonable action necessary to temedy
Why should you try to ensure T keeps control if L does depart from plans
Ensures premises remain appropriate for occupation + delay is not excessive
Kilmartin v Safeway said what
‘Usable’ area is for sensible purpose in connection w/ proposed occupation - included entrance ramp but not fire exits or lift
What kind of notice for A4L is more vulnerable
Unilateral
Two things to check for A4L + lease, prior to completion
Prepare engrossments + annexures, and ensure both sides have signed
When do CWs become important
When DLP runs out
What is the nature of A4L and what does that mean - personal or tied to land?
Personal, so T cannot require L to grant to 3rd, and L’s Os cannot be enforced against successor L
T’s payment obligations if supply of services to L
T accounts to HMRC for VAT on inducement
If L is to carry out works, how to deal w/ T’s supervision?
Surveyors to enter at 3 points - sufficiently complete for occupation, practical completion + final completion. Can also state ‘at reasonable times’ w/ no limit. T to give reasonable written notice.
Provisions for T to carry out works in A4L are the same as in what doc, done after completion as part of property management
Licence to Alter
Why deal w/ delay provisions through force majeure + LADs if L to carry out work
Some issues not within L’s control so no damages, but should pay damages if within control.
What are the four ‘Quarter Days’
25 March, 24 June, 29 September, 25 December
If land is multi-let, who keeps the CDM Regs folder
L
Who must be joined to A4L or not bound to give guarantee on completion
Guarantor
Why ensure that T can supervise L’s works?
Constant supervision of work ensures keeping w/ agreement + verified by agent of T (rather than of L)
Why should premises be measured by independent party
To avoid disputes
What will L want to get if has to pay VAT on inducement given to T
VAT invoice
What is the procedure under 38(1) LTA if 14 day gap before T bound
Warning notice served on T (+ G) + T (+G) signs simple declaration
When is Completion Statement prepared
After exchange of A4L, prior to completion.
Two differences between agreed and unilateral notices
Agreed is public (unless Exempt Info), and requires consent of proprietor
When is A4L negotiated
W/ lease
What is the surveyor’s method
Take yearly rent (separating out each charge in ‘Rents’), add any VAT, divide by 365, then times by number of days to next QD
What should measuring provision state if parties cannot resolve their differences
Explicitly set out independent party to go to
Is there a tolerance level under Kilmartin/6th edition RICS
No - below or above the limits = no tenancy, or capped rent
Round to how many decimal places for each stage in surveyor’s method
Two
Why deal w/ measuring provisions through 6th edition RICS
Certainty
In what two circumstances will L want to terminate A4L
If T insolvent, or if T fails to complete on agreed date
How to avoid A4L being public on LR
EX1 + EX1A for Exempt Info
How to define ‘Access Date’ when T to carry out works
Architect to verify stage when T can enter - Premises completed to reasonable satisfaction of architect
Two possible definitions for ‘Term’ in A4L
From lease being granted, or when T occupies
In surveyor’s method, when do you count from and to
Include completion but exclude next QD
What can be obtained to avoid T being liable for construction defects
CWs from whole Professional Team + architect
If L is to carry out works, how to define standard of construction
Good and workmanlike manner, w/ good quality materials or such other materials as are substantially similar
What is T granted to carry out works before lease completed
Mere licence w/o ability to trade
If T is required to reinstate, what should you ensure regarding RR
Provision is considered at RR
What two things could be explicitly stated to help w/ measuring under Kilmartin + 6th edition RICS
State use contemplated + ‘Internal Area’