2 - Domestic Retrofit Information Flashcards
1 What is meant by the abbreviation EEM?
Environmental energy
measures
Energy-efficiency measures
Energy environmental measures
Environmental efficiency measures
Energy-efficiency measures
The part of the Building Regulations that cover the conservation of fuel and power in existing dwellings is:
Part L1B
Part L1A
Part L2A
Part L2B
Part L1B
The type of brickwork bond shown in this image is:
Stretcher bond
Flemish bond
Garden wall bond
English bond
English Bond
One way for telling if a ground floor is suspended is the use of:
Weep holes
Brick bond
Air bricks
Damp-proof course
Air bricks
New gas boilers must reach a minimum efficiency of:
65%
80%
85%
92%
92%
Contain detailed written information that covers construction, features, materials, finishes and performance requirements for each major aspect of a project.
Specifications
Work programmes
Purchase orders
Invoices
Specifications
Are detailed breakdowns of the order in which the work needs to be completed, with an estimate of how long each stage will take i.e. activity against time.
Specifications
Work programmes
Purchase orders
Invoices
Work Programme
Are issued by a buyer to a supplier.They detail the type of materials, quantities and agreed price, so form a good record of what been agreed.
Specifications
Work programmes
Purchase orders
Invoices
Purchase orders
Are lists of materials or services that have been provided by the contractor.
Specifications
Work programmes
Purchase orders
Invoices
invoices
Which of the following trades is most likely to carry out photovoltaic (PV) installations?
Plumber
Electrician
Heat engineer
General builder
Electrician
In the construction industry, what percentage of companies employ between 1 and 13 people?
1%
4%
80%
90%
90%
Establishing costs for labour, plant, equipment and materials for a construction project is mainly the job of:
An estimator
A planner
A site engineer
A buyer
An estimator