2-6-12 Underground Installations – Caissons Flashcards

1
Q

Utility locates must be completed __?__.

A

before digging begins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When the pole base hole turns out to be larger than expected, a __?__ may be used to maintain the diameter of the caisson.

A

sono tube

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The diameter of #5 rebar is __?__.

A

5/8”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Rebar measuring 11/8 inches in diameter would be referred to as __?__ bar.

A

9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Rebar adds __?__ strength to the caisson.

A

structural

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The anchor bolt pattern for the caisson is determined by the __?__.

A

pole manufacturer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If anchor bolts are assembled in a jig, they do not have to be aimed.

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which part of the rebar cage should be in contact with the earth?

A

No part

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

To eliminate any voids, a concrete __?__ is used during the pour to consolidate and move the concrete around the hole.

A

vibrator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Concrete needs to cure three to seven days before a pole and mastarm may be installed in the base.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

At an intersection that is askew, the mastarm is set parallel to the opposing cross street.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When building a rebar cage, a __?__ is used to join the steel pieces together.

A

tie wire

How well did you know this?
1
Not at all
2
3
4
5
Perfectly