15 - Contract Administration Flashcards
Contract Administration - Extract from Candidate Guide - Aug 2018 (updated Feb 2022)
What is phased completion ?
Construction works can be planned as a series of stages or phases, rather than as one continuous process.
This can be useful for clients where a complex sequence of events needs to be followed (such as on densely occupied or complex site), or where there are a number of distinct components to the works, particularly for clients who are seeking to maintain some level of business operation during construction and so wish to minimise disruption.
In such cases, the project works can be divided into a series of smaller projects, spaced out over a period of months or even years.
What is sectional completion ?
Sectional completion refers to a provision within construction contracts allowing different completion dates for different sections of the works. This is common on large projects that are completed in sections, allowing the client to take possession of the completed parts whilst construction continues on others.
What are the risk associated with a client paying for items direct and outside of the contract ?
They would not be included within the contract, contract administrators inspection and have limited protection.
Can you please expand on what the role of a Contract Administrator is ?
A contract administrator manages contracts made between building contractors, employers, and clients. Their responsibility is to administer construction contracts, whereby they may act as project managers, engineers, consultants and client representatives
Can you expand on your knowledge of the JCT Intermediate contract ?
A JCT contract that allows for a number of addition in comparison to JCT MW including, clerk or works, sectional completion, partial possession, sectional completion, the use of bonds.
Can you expand on your knowledge of the JCT Standard Building Contract
The JCT SBC allows for additional to the intermediate contract such as:
Employers representative, listed sub contractors, retention bonds, variation and acceleration quotations, third party rights.
What JCT contracts allow for a clerk of works ?
- JCT Standard building contract
- JCT Intermediate Contract
- Not JCT MW
What contract allow for sectional completion and named sub contractors ?
Intermediate and standard building contract
Can you talk me through the EOT timeline ?
Can you explain the interim payment procedure under JCT MW ?
Can you explain the final payment procedure under JCT MW ?
When can a employer claim for liquidated damages (JCT MW) ?
What is the ‘Guide to select the appropriate JCT Main Contract ‘?
What is contract between the main contractor and the sub contractor ?
In this scenario is was a bespoke contract, the sub contractors were dealt with as domestic subcontractors and the responsibility of the main contractor.
Does JCT MW allow for clerk of works ? What contracts do allow for this ?
No it does not however, both intermediate and standard building contracts do allow for this.
What are the main types of tendering ?
- Open
- Selective
- Negotiated
- Serial
- Framework
What are the main updates from the previous version (JCT MW updates) ?
JCT MW 2016 updates include :
• Amendments to reflect CDM 2015
• Increased flexibility regarding insurance and ‘insured by other means’
• Simplified payment provision including the interim payment provision under the Housing Grant, Construction and Regeneration Act 1996
What is a traditional lump sum contract ?
A lump sum contract is the traditional means of procuring construction, and involves a single ‘lump sum’ price for all the works being agreed before the works begin. This means that the contractor is able to accurately price the works they are being asked to carry out.
What is the role of the contract administrator ?
To administer the conditions/works under the terms of the contract. Acting impartially.
What is a contract instruction and how would you deal with it ?
In simple terms, a contract variation occurs when the parties agree to do something differently from the way they originally agreed, whilst the remainder of the contract otherwise operates unchanged. Such an agreement, if valid, would amount to a variation of the existing contract.
What is traditional procurement ?
Traditional procurement remains the most commonly-used method of procuring building works. It comprises a tripartite arrangement involving a client, consultants and contractor.
The traditional procurement route involves separating design from construction. The client first appoints consultants to design the project in detail and to ensure cost control and inspect the construction works as they proceed. Contractors are then invited to submit tenders for the construction of the project on a single-stage competitive basis.
Included in the contractor’s responsibilities are workmanship, materials and work undertaken by suppliers and subcontractors. The contractor is not responsible for the design (other than temporary works), although some traditional contracts may provide for the contractor to design specific parts of the works (see key criteria below).
Traditional procurement is typically undertaken under a lump sum contract. A single ‘lump sum’ price for all the works is agreed before the works begin, then stage payments are made as the works proceed. This is appropriate where the project is well defined when tenders are sought, and significant changes to requirements are unlikely. This allows the contractor to accurately price the works they are being asked to carry out.
What are the others available JCT Contracts ?
- Standard Building Contract;
- Design & Build;
- Intermediate Contract;
- Intermediate Contract with Design;
- Minor Works;
- Minor Works with Design;
- Major Projects (MP)
- Framework, non-binding and binding;
What is a letter of intent ?
A letter of intent is a document outlining the understanding between two or more parties which they intend to formalize in a legally binding agreement. The concept is similar to a heads of agreement, term sheet or memorandum of understanding