10. Termination Flashcards
Two scenarios wherein the right to terminate arises
- Breach of a condition
- Very serious breach of an innominate term (repudiatory breach)
If one party breaches a condition in the contract, does it automatically terminate?
No, the innocent party has a choice to affirm the contract or treat it as over
If a party decides to affirm a contract and later wishes to change their mind and terminate - can they do this?
No, affirmation is a bar to terminating a contract
Does a breach of a contractual warranty give rise to the right to terminate?
No, but it gives rise to a claim in damages
If the innocent party affirms a contract wherein a condition has been breached - are they barred from pursuing damages?
No, they can pursue damages for loss from the breach
Can a contract be terminated if performance is complete?
No, termination only operates to discharge parties from future contractual obligations
Doctrine of Frustration: what is it and when is it relevant
- The contract is automatically brought to an end
- Due to an unforeseen event beyond either party’s control
- the law determines how loss should be borne by the parties
When will a change of circumstances leading to an inability to complete a contract amount to ‘frustration’
- The event makes performance of the contract impossible or radically different
- is beyond the ordinary risks the parties considered when making the contract
- was entirely beyond the control of either party
Under what circumstances could the performance of the contract be rendered ‘radically different’ (wrt frustration)?
- government intervention
- unavailability of a specific person crucial to the contract
- illegality
- destruction of the subject matter
- non-occurence of a fundamental event
(in all cases will be a question of degree)
When will ‘delay’ frustrate a contract?
- if there is a contractual provision for delay which does not cover a delay of this scale
- the delay is very long relative to the duration of the contract
- the delay means obligations in the contract cannot be performed on time
- the performance resumed is radically different from the contract
What is a ‘force majeure’ clause
Contractual clause providing for the occurrence of ‘unexpected events’ and ‘excusing’ non-performance
- will not be able to rely on doctrine of frustration if event is covered in this clause
Requirements for Force Majuere clause to be binding?
must comply with s 3 UCTA 1997 (pass the reasonableness test) in order to be upheld
If a contract is frustrated but money has already been paid under the contract - can this money be recovered / need outstanding money still be paid?
- Money paid before the event can be recovered
- Money that should have been before the event need not be paid
- at the court’s discretion, expenses occurred from either can be recovered out of the total sums paid / payable before the event (WIDE)
- if one party has conferred a valuable benefit on another before frustration, court may order a just sum be paid to them
If a contract is frustrated, what is the maximum the court can award for expenses incurred by the payee?
A sum equal to the total paid and payable before frustrating event OR the amount of the expenses incurred (whichever is lower)