____ plants should always be used if maintenance planning is carried out centrally in one plant for several
plants. If every plant is independent in maintenance terms, then each plant is also a planning plant at the same time.
Planning
In Plant Maintenance, a distinction is made between the organizational units “planning plant” and “maintenance plant”.
• Maintenance plant
In a maintenance plant, you can manage technical objects and main work centers.
• Planning plant
In the planning plant, maintenance task lists are defined for the respective maintenance plants, material planning is
carried out on the basis of bills of material in task lists and orders, maintenance plans are managed and scheduled,
maintenance notifications are created and maintenance orders can be handled.
A ___ is the organizational unit responsible for planning maintenance activities.
Planning Plant
All technical objects (functional location, equipment and serial number) to be maintained are physically present in a ____.
Maintenance Plant
___ perform maintenance tasks or are responsible for such tasks.
Work Center
A maintenance ___ is responsible for planning maintenance tasks.
Planner group
A ____ is used to label the physical placement of a technical object.
Location
You define the responsibilities associated with operating the production plant as a ____.
Plant Section
Plants are assigned to a ___ which are subsequently assigned to a ___.
Company code
Controlling Area
A ____ is the the smallest organizational unit for which a complete, self contained set of accounts can be drawn for the purposes of external reporting.
Company Code
The ____ is an organizational unit within a company. It is used to represent a closed system for cost accounting purposes.
Controlling Area
When you assign a technical object to a maintenance plant, you not only create its ___, but you also determine its ____.
Company code
Controlling area
When you assign a work center to a plant, you also determine its ____.
Controlling area
From a maintenance perspective, a ____ represents an individual person or a work shop (such as a paint shop, cleaning line, mechanical workshop, etc.)
Work Center
In plant maintenance, ____ are used in equipment masters, maintenance items, maintenance task lists, operations of a maintenance task list, notifications, order header and operations of an order.
Work Center
You use transaction ___ to maintain work centers.
IR01
Name some of the tabs on a work center
Basic Data
Default Values
Scheduling Data
Availability Capacity
The ____ (in the default values) is used to determine in the maintenance order to tell whether:
- the operation should be a part of costing
- the operation should be scheduled
- the operation should generate capacity requirements
- the operation should be processed externally
- service specifications should be set up in the operation
Control Key
Work center contains schedule data for ____ scheduling.
Lead time
Available ___ specifies which service provides the ___ for each work day.
Capacity
____ contain costing data that enables you to cost operations.
Work centers
What is th most frequently used structuring sequence?
Functional Location -> Equipment -> BOM