09 Claims Flashcards
What is an extension of time?
???
Do all delays give rise to an extension of time?
???
As CA, what is the process in assessing if a contractor is due an extension of time?
???
What are relevant events?
???
List some typical relevant events.
- Variations
- Failure to provide information
- Discrepancies in the contract documents
- Delay in giving the contractor possession of the site
- Exceptionally adverse weather
- Force majeure (events beyond the reasonable control of a party, such as a war or epidemic)
- Loss from a Specified Peril as listed in the contract (e.g. flood, earthquake etc.)
- Civil commotion or terrorism
- Opening up works (unless the inspection shows that the works are not in accordance with the contract)
How would you establish what constitutes exceptionally adverse weather?
???
Do relevant events incur cost?
???
What is loss and expense?
???
How would you go about assessing a claim for loss and expense?
???
What are relevant matters?
???
What is the difference between a relevant event and a relevant matter?
???
List some typical relevant matters.
- Variations
- Delay in giving the contractor possession of the site
- Opening up works (unless the inspection shows that the works are not in accordance with the contract)
- Discrepancies in the contract documents
- Any impediment of the Contractor caused by the Employer, CA or QS, whether by an act or omission, except to the extent caused or contributed by any default
Who is responsible for establishing claims for extensions of time and loss and expense?
???
How would you go about establishing how long an extension of time to grant a contractor?
???
How are extensions of time and loss and expense dealt with under NEC forms of contract?
???
Would you expect to see a claim for loss and expense from the contractor at the end of an NEC contract and why?
???
Can you use BQ rates to calculate a claim for loss and expense?
???
When would you use Hudson?s or Emden’s formula in calculating a claim?
???
If you were assessing a claim for loss and expense, what would be the impact of concurrent events?
???
If a contractor came to you with a claim for loss and expense, would you automatically review it or would you talk to anyone first?
???
On a project where there is a valid claim for loss and expense, but where you have not agreed a final figure with the contractor, how would you deal with including monies in an interim valuation?
???