01 Procurement Flashcards

1
Q

What is involved in the procurement process?

A

Procurement is the overall act of obtaining goods and services from external sources (i.e. a building contractor) and includes deciding the strategy on how those goods are to be acquired by reviewing the client’s requirements (i.e. time, quality and cost) and their attitude to risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What factors should be considered when deciding on the appropriate procurement method?

A
  1. Time - required completion date
  2. Cost - funds available
  3. Quality - required performance
  4. Risk allocation for time, cost and quality
  5. Type of project - complexity, requirement for contractor input etc.
  6. Level of client input
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the main procurement routes.

A
  1. Traditional lump sum method
  2. Management contracting
  3. Construction management
  4. Design and build
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How does a traditional procurement route work?

A
  • The contractor agrees to build the design supplied by the employer and therefore has no responsibility for design
  • Appropriate where the objectives of the employer have been clearly determined
  • Financial outcome, responsibility and risk usually reside with the employer
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the advantages and disadvantages of a traditional procurement route?

A

Advantages:

  1. Familiarity with most employers and contractors
  2. High degree of design and product control/selection
  3. Robust variation control
  4. Direct employer relationship with designers

Disadvantages:

  1. Time - longer project delivery
  2. Split responsibility between construction and design
  3. Limited risk transfer/increased economic uncertainty
  4. Limited opportunities to refine design and improve cost efficiency
  5. Potentially more likely to lead to disputes (e.g. designer vs contractor)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How does a design and build procurement route work?

A
  • Tender documents outlining the employer’s requirements are prepared by consultants employed by the client
  • A single contractor is then appointed (usually through a two-stage tender process), who will deliver to the requirements as outlined and take on responsibility for both design and construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the advantages and disadvantages of a design and build procurement route?

A

Advantages:

  1. Cost certainty - total cost is established from the outset
  2. Single point responsibility - design, cost and programme all lie with the contractor
  3. ‘Buildability’ issues can be resolved through contractor design involvement
  4. Time - potential to overlap design and construction stages

Disadvantages:

  1. Loss of design control - may be cost-driven rather than quality-driven
  2. Restricted scope for change post-contract (without paying a premium)
  3. Longer tender evaluation period to ensure contractor’s proposals meet the employer’s requirements
  4. Higher tendering costs for contractors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How does a management contracting procurement route work?

A
  • Management contractor is appointed on the basis of a fixed management fee (often a percentage project value) and rates for staff costs and common user facilities
  • The management contractor programmes, packages and obtains tenders for the work, which are each let on a competitive basis
  • The management contractor then has a direct contractual relationship with works contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the advantages and disadvantages of a management contracting procurement route?

A

Advantages:

  1. Less confrontational
  2. Contractor involvement to advise on buildability issues
  3. Time - can allow earlier start on site
  4. Flexibility to develop design whilst inviting tenders and letting packages
  5. An advantage over construction management - payments to the supply chain are made by the contractor, so the client avoids the administration inherent in making such payments

Disadvantages:

  1. Cost and programme risk lies with employer - not defined until all packages are let
  2. Greater employer involvement through rolling decision-making
  3. Design content needs to be precisely detailed prior to commencement, in order to minimise works that fall between packages
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How does a construction management procurement route work?

A
  • Similar to management contracting, however the project is split into packages and the client enters into separate contracts with each works contractor
  • The client appoints a management team and a construction manager on a fee basis, obtained in competition, who would be expected to co-ordinate the design and construction programmes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the advantages and disadvantages of a construction management procurement route?

A

Advantages:

  1. Less confrontational
  2. Contractor involvement to advise on buildability issues
  3. Time - can allow earlier start on site
  4. Flexibility to develop design whilst inviting tenders and letting packages
  5. Direct employer relationship with the works contractors - can lead to improved performance

Disadvantages:

  1. Increased risk to employer - little risk carried by the construction manager
  2. Cost and programme risk lies with employer - not defined until all packages are let
  3. Reduced single-point responsibility
  4. Higher level of client administration, and consequent cost, throughout the contract period
  5. Design content needs to be precisely detailed prior to commencement, in order to minimise works that fall between packages
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are framework agreements?

A
  • Used for when employers who carry out work regularly wish to try and capture the benefits of long term relationships within the supply chain
  • Open tenders are usually advertised for firms to apply to be on a framework and eventually a smaller framework of approved contractors/consultants
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How can you ensure value for money on a framework agreement?

A

Once the framework/approved list is agreed, contractors will usually be appointed in one of two ways:

  1. Calling off based on agreed fees - fee scales/rates based on project size/complexity
  2. Mini tenders - in effect an approved-supplier list, whereby the shortlist still has to go through the process of a mini competitive tender
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the advantages and disadvantages of framework agreements?

A

Advantages:

  1. Reduced procurement time and costs for large numbers of contracts of similar works
  2. Early contractor involvement
  3. Provide greater continuity potential work and thus increase competiveness
  4. Partnering benefits allowed to grow and accumulate

Disadvantages:

  1. Having already been appointed on a framework agreement, suppliers may have to bid again for individual projects anyway, which can be timely and costly
  2. Complacency if contractors are guaranteed repeat work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you establish the relevant client?s requirements when deciding on a procurement route?

A

???

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the contractual links for the client in each of the main procurement routes?

A

???

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Which form of procurement will give a client the maximum cost certainty?

A

???

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How can you introduce cost certainty into a procurement route?

A

???

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

If a client wished to pass on his concept design team to a design and build contractor, how could this be achieved?

A

???

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is novation and how does it differ from assignment?

A

???

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Explain to a client how the process will work when his design team are novated to his design and build contractor.

A

???

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

A design team has been novated to a design and build contractor. The contractor wants to re-negotiate their fees as part of the novation. Can he do this?

A

???

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Who has design responsibility under a MC or CM procurement route?

A

???

24
Q

What are the main consultant appointments under each of the main procurement routes?

A

???

25
Q

What role do you play under each of the main types of procurement?

A

???

26
Q

What is the role of the contract administrator under each of the main types of procurement?

A

???

27
Q

Explain why the procurement route used on one of your projects was suitable.

A

???

28
Q

Your client will be borrowing money to build industrial units as and when he has a pre-let. As such, he wants to mobilise quickly to get the buildings completed as soon as possible. What would be a suitable procurement route and why?

A

???

29
Q

A client?s main interest on a project is the cost. Explain to him what level of cost certainty and cost control you would expect from each of the main types of procurement?

A

???

30
Q

A client’s hotel has been damaged by fire and the refurbishment will be funded through an insurance claim. He is more interested in getting it done quickly than in how much it costs. What would be a suitable procurement route and why?

A

???

31
Q

If a client wanted to take the benefits of a design and build procurement route but also wanted to have some degree of control over the design of the building, how could this be achieved?

A

???

32
Q

If a client wished to pass on his concept design team to a design and build contractor, how could this be achieved?

A

???

33
Q

Your client is a Housing Association developing a site with 85 houses. What advice would you give them regarding procurement?

A

???

34
Q

What is partnering?

A

???

35
Q

How does project partnering differ from strategic partnering?

A

???

36
Q

What benefits can partnering bring to a project?

A

???

37
Q

What are the criticisms associated with partnering?

A

???

38
Q

Is partnering contractually binding on the parties?

A

???

39
Q

Explain how partnering has benefited one of your projects.

A

???

40
Q

A client is curious about partnering. He wants to know how popular it is in the construction industry and if it really works. Give him some advice.

A

???

41
Q

A client likes the idea of partnering, but wants to know if he should make it contractually binding. Give me some advice.

A

???

42
Q

Explain the concept of the Private Finance Initiative.

A

???

43
Q

Explain how the new PF2 differs from the old PFI.

A

???

44
Q

Why is whole life costing important to the PFI process?

A

???

45
Q

How does maintenance planning affect PFI?

A

???

46
Q

How might a building surveying practice get involved with the process of PFI?

A

???

47
Q

How do market trends and location effect the cost of construction?

A

???

48
Q

What is Prime Contracting?

A

???

49
Q

Explain the concept of lean construction.

A

???

50
Q

How and why should the supply chain be involved in a project?

A

???

51
Q

Give an example of how you have been involved in setting the procurement strategy on a project.

A

???

52
Q

Explain how selecting the best procurement strategy has benefited a client on one of your projects.

A

???

53
Q

Explain how a client’s level of construction experience has influenced your recommendation of a procurement strategy.

A

???

54
Q

Explain how your role as a surveyor has varied under different procurement strategies.

A

???

55
Q

What would you expect to see in a procurement strategy report?

A

???

56
Q

A client asks you to demonstrate how you are achieving best value in the procurement of his project. How would you do this?

A

???