Which project management process group continuously improve; perform progressive elaboration?
Executing
Logical breakdown of what you need to do to produce the deliverables of the project.
Project Life Cycle
Which project management process group finalizes procurement strategy and documents?
Planning
Which project management process group develops assumption log?
Initiating
Which project management process group produces product deliverables (product scope)?
Executing
A form of progressive elaboration.
Rolling Wave Planning
Which process updates the resource management plan, as well as resource-related documentation?
Control Resources
Which process creates and implement workarounds?
Monitor Risks
Which process confirms the type and quantity of resources used are consistent with what was planned?.
Control Resources
Which project management process group determines the critical path?
Planning
The process of continually refining estimates and scope definition.
Progressive Elaboration
Which project management process group selects a project manager?
Initiating
Which project management process group is the only process group with a set order?
Planning
Which process assess whether stakeholders’ expectations are aligned with the project?
Monitor Stakeholder Engagement
The goal is to produce the project deliverables within the project’s planned budget and schedule to deliver the agreed upon benefits.
Executing Process Group
Which project management process group facilitates conflict resolution?
Executing
If a high-priority project has a tight schedule that does not allow much room for variance, the project will require more what than a low-priority project with a fairly flexible schedule?
Planning
Which process reassess risks, planned risk responses, and risk reserves?
Monitor Risks
Which process updates the quality management plan, as well as quality- and process-related documentation?
Control Quality
The person who should be in control of the project during project planning is the:
A. Project manager
B. Team member
C. Functional manager
D. Sponsor
Answer A
Explanation The project manager should be named early in the project, during project initiating if
possible. It is then their responsibility to control the project throughout its life.
Which project management process performs risk reviews, reassessments, and audits?
Monitoring & Controlling
It is the performing organization’s or department’s methodology for managing a project.
Project Life Cycle
The best time to assign a project manager to a project is during:
A. Integration
B. Project selection
C. Initiating
D. Planning
Answer C
Explanation The project manager should be assigned during project initiating.
Which process reports on seller performance compared to contract?
Control Procurements
Which process requests changes or improvements to work and processes?
Control Quality
Which project management process group creates project scope statement?
Planning
Which process analyzes information about communications to make sure they are meeting stakeholder needs?
Monitor Communications
Which project management process approve or reject changes?
Monitoring & Controlling
A progression of phases through a series of developmental stages.
Project Life Cycle
Which process identifies new risks?
Monitor Risks
At the end of each phase, an event called what may take place?
A phase gate
Which project management process group acquire final team and physical resources?
Executing
Which project management process group completes financial closure?
Closing
Which process watches for the occurrence of risk triggers?
Monitor Risks
Which project management process group follow processes?
Executing
At what point is a project considered closed?
Closing Process Group
- After the administrative pieces of project closure are completed and the customer, sponsor, and other stakeholders provide formal sign-off that the product of the project is acceptable, the project is closed. At that point, any team members utilized to close the project or project phase are released.
Which process group includes administrative activities such as collecting and finalizing all the paperwork needed to complete the project, and technical work to confirm that the final product of the project is acceptable?
Closing Process Group
A project life cycle where the project scope is generally determined early in the project life cycle, but time and cost estimates are routinely modified as the project team’s understanding of the product increases.
Iterative Life Cycle
- Iterations develop the product through a series of repeated cycles, while increments successively add to the functionality of the product.
Historical information is collected throughout the project, but it is during this process that the final versions of the lessons learned are compiled and archived in the lessons learned repository.
Closing Process Group
Which project management process group perform risk identification, qualitative and quantitative risk analysis, and risk response planning?
Planning
Used to manage the requirements that are less clear.
An adaptive life cycle
Which process
Control Schedule
Used to manage the project requirements that are well defined.
A predictive life cycle
Which project management process group gain formal approval of the plan?
Planning
Which process measure schedule performance against the performance measurement baseline.
Control Schedule
Which project management process group assess what to purchase and create procurement documents?
Planning
All the following occur during the planning process group except:
A. Develop Project Charter
B. Create WBS
C. Estimate Costs
D. Sequence Activities
Answer A
Explanation Develop Project Charter occurs in project initiating.
Phases are collectively referred to as the development life cycle of a project and used to ensure that the expected or planned result of each phase is achieved.
Project Life Cycle
- An example of a development life cycle for a software project might include the following life cycle phases: research, design, code, test, and implement.
Which project management process group evaluates sellers as well as negotiates and contracts with sellers?
Executing
Which project management process group develops the budget?
Planning
Which process group is high-Level planning performed?
Initiating
Sign-off and acceptance are important in this process group because they confirm that the customer considers the project completed and accepts the whole project.
Closing Process Group
- Imagine the team never gains formal acceptance on a project for an external customer, but moves on to other projects. Then the customer calls for additional scope to be added to the project.
A project manager has received some help from the team, and she needs help from them again so that
she can create a detailed project budget. Which project management process group is she in?
A. Initiating
B. Before the project management process
C. Planning
D. Executing
Answer C
Explanation Notice the use of the word “detailed:’ Such a budget is created during project planning.
Which project management process group determines quality standards, processes, and metrics?
Planning
Measuring customer satisfaction is an important part of which process group?
Closing Process Group
Which process validates contract changes, control contracts to updated versions, and evaluate effectiveness of changes?
Control Procurements
Which project management process group completes final performance reporting?
Closing
Which project management process group develops the schedule?
Planning
Which project management process group holds team-building activities?
Executing
If the decision is made to move forward, the project would begin initiating work on the next phase and progress through the project management process groups for that phase.
A phase gate
• Uses incremental, iterative, or adaptive (agile) development life cycles, and have varying levels of early planning for scope, schedule, and cost.
Change-Driven Project Life Cycle
Work is planned in short increments to allow the customer to change and reprioritize requirements within the time and cost constraints.
Adaptive (agile) development life cycles
Which project management process group develops realistic and sufficient project management plan and baselines?
Planning
What are the 24 actions required to complete Project planning?
• Develop Project Management Plan (Integration Management chapter)
- Plan Scope Management (Scope Management chapter)
- Collect Requirements (Scope Management chapter)
- Define Scope (Scope Management chapter)
- Create WBS (Scope Management chapter)
- Plan Schedule Management (Schedule Management chapter)
- Define Activities (Schedule Management chapter)
- Sequence Activities (Schedule Management chapter)
- Estimate Activity Durations (Schedule Management chapter)
- Develop Schedule (Schedule Management chapter)
- Plan Cost Management (Cost Management chapter)
- Estimate Costs (Cost Management chapter)
- Determine Budget (Cost Management chapter)
- Plan Quality Management (Quality Management chapter)
- Plan Resource Management (Resource Management chapter)
- Estimate Activity Resources (Resource Management chapter)
- Plan Communications Management (Communications Management chapter)
- Plan Risk Management (Risk Management chapter)
- Identify Risks (Risk Management chapter)
- Perform Qualitative Risk Analysis (Risk Management chapter)
- Perform Quantitative Risk Analysis (Risk Management chapter)
- Plan Risk Responses (Risk Management chapter)
- Plan Procurement Management (Procurement Management chapter)
- Plan Stakeholder Management (Stakeholder Management chapter)
The WBS and WBS dictionary have been completed, and the project team has begun working on
identifying risks. The sponsor contacts the project manager, requesting that the responsibility
assignment matrix be issued. The project has a budget of $100,000 and is taking place in three countries
using 14 human resources. There is little risk expected for the project, and the project manager has
managed many projects similar to this one. What is the next thing to do?
A. Understand the experience of the sponsor on similar projects.
B. Create an activity list.
C. Make sure the project scope is defined.
D. Complete risk management and issue the responsibility assignment matrix.
Answer B
Explanation Look at the order of planning the project that the team has chosen. Although
understanding the experience of the sponsor might sound like a good idea, the sponsor is a stakeholder,
and understanding the stakeholders is part of stakeholder analysis. That should have occurred before
the creation of a WBS. Project scope must be defined before a WBS can be created. Completing risk
management and issuing the responsibility assignment matrix cannot be best, as that work does
not come next in the process. Other work must be done before risk management can effectively be
completed. Creating an activity list comes next after the WBS and WBS dictionary.
Which project management process group uses and shares project knowledge?
Executing
Which project management process manages, evaluates, and closes procurements?
Monitoring & Controlling
A project manager does not have much time to spend on planning before the mandatory start date
arrives. He therefore wants to move through planning as effectively as possible. What advice would
you offer?
A. Make sure you have a signed project charter and then start the WBS.
B. Create an activity list before creating a network diagram.
C. Document all the known risks before you document the high-level assumptions.
D. Finalize the quality management plan before you determine quality metrics.
Answer B
Explanation This question is asking which of the choices is the most effective way to move through
project planning. Starting the WBS immediately after obtaining a project charter skips the important
steps of defining the scope and other activities. High-level assumptions are determined in project
initiating. Qyality metrics are determined as part of the quality management plan, not after it. The
activity list is created before the network diagram, so that is the best option.
Which process ensures information is being communicated to the appropriate people in the right way and at the right time?
Monitor Communications
Which project management process group sends and receives information, and solicits feedback?
Executing
The results are the project management plan and project documents that will guide the execution and control of the project.
The planning effort
Delivers a complete, usable portion of the product for each iteration.
An incremental development life cycle
- For example, a project to build a website using an incremental life cycle would involve prioritizing requirements into iterations that deliver a fully functioning portion of the website at the end of each iteration.
Which project management process performs quality control?
Monitoring & Controlling
Which process group confirms that all the requirements have been met?
Closing Process Group
- Most studies show that many requirements are not met on projects, especially on projects with numerous pages of requirements.
Which project management process group requests changes?
Executing
Which project management process group executes contingency plans?
Executing
A combination of a predictive and an adaptive development life cycle.
Hybrid Development Life Cycle
Which of the following is a characteristic of project management processes?
A. Iterative
B. Unique
C. Unnecessary
D. Standardized
Answer A
Explanation As the project life cycle progresses, more information becomes available, allowing the
team to manage the project to a more detailed level.
Which project management process group create measurable objectives and success criteria?
Initiating
‘The high-level project schedule constraints have just been determined. What project management
process group are you in?
A. Initiating
B. Planning
C. Executing
D. Monitoring and controlling
Answer A
Explanation High-level constraints are identified in the project charter, which is created during
project initiating.
A project life cycle that is iterative or incremental.
Adaptive Life Cycle.
Which project management process group creates the WBS and WBS dictionary?
Planning