03 - Developing Flashcards

1
Q

Is an early compilation of the significant work items that will have associated cost or schedule considerations.

A

Work breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Is defined as a task-oriented, detailed breakdown of activities that organizes, defines, and graphically displays the total work to be accomplished to achieve the final objective of a project

A

Work breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Is a breakdown or hierarchical representation of the various costs in a project

A

Cost breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Represents the costs of the components in the work breakdown structure

A

Cost breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Is a critical tool in managing and the financial aspects of any project and created a structure for applying measurable cost controls

A

Cost breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Is the determination of the timing and sequence of operations in the project and their assembly to give the overall completion time

A

Scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

An uncertain event or condition that, if it occurs, has a positive or negative effect on at least one project objective, such as time, cost, scope, or quality,

A

Risk analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Extra time

A

Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A project management tool in which the stages of a project are graphically represented on a chart.

A

Project evaluation and review techniques (PERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A network analysis technique that allows for conditional and probabilistic treatment of logical relationships

A

Graphical evaluation and review technique (GERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Common scheduling errors

A
  • redundant relationships
  • logic loop
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

An event oriented network analysis technique used to estimate project duration when there is a high degree of uncertainty with individual activity duration estimates

A

PERT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Applied the critical path method to a weighted average duration estimate

A

PERT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Is a modification of the traditional GERT approach in that is recognizes special circumstances where multiple number of the project teams or activities must be taken into consideration simultaneously

A

Queue-graphical evaluation and review technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

was the first simulation language which allowed a modeler to formulate a system description using process, event, or continuous world views or any combination of the 3

A

Simulation language for alternative modelling (SLAM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which has been developed to help prepare a robust construction plan, focusing on construction feedbacks in dealing with indirect and unanticipated events during construction

A

Dynamic planning and control methodology (DPM)

17
Q

Is a project management methodology that helps you monitor essential resources and prioritize dependent tasks within a project

A

Critical chain planning

18
Q

The extra time that’s placed between the final task and the end of the project

A

Project buffers

19
Q

The extra time that’s placed between the feeding chain(non critical chain) and the critical chain.

A

Feeding buffers

20
Q

These are literal resources you set aside in case the critical chain is in need of extra supplies— like extra team members to have on hand, additional equipment, or help from a third-party

A

Resource buffers

21
Q

Is the full amount of assigned hours you have tasked your team with divided by the number of hours you have to do the work

A

Resource loading