020303aAB Interior Systems And Door Frames Flashcards

1
Q

Structural metal studs can be used for buildings up to 5 storeys. T or F

A

T

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Loadbearing metal framing components are made of hot dipped galvanized steel in which gauges?

A

20, 18, 16 and 14

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Non-loadbearing framing systems are made of ___, ____ and ____ gauge galvanized steel.

A

25, 22 and 20

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Runners should be the same gauge as the steel studs (or heavier). T or F

A

T

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Flanges for sheet steel stud wall framing should have flanges be at least ____.

A

30 mm (1-3/16”)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Any runners must be attached to the building at approx. ____ from their ends and at _____ o.c spacing for interior walls or ____ for exterior walls.

A

50 mm, 24”, 12”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which explosive actuated too fastener us suitable for anchoring a pin in a concrete ceiling for hanging a suspended ceiling?

A

Eye pins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are two wall anchors used to hold a metal door frame in a concrete block wall?

A

Wire mason anchors and metal strip masonry anchors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are hold-down clips used for?

A

To hold fire-rated ceiling tile in place.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How much clearance is require for placement of ceiling tiles?

A

Leave clearance for recessed lights, ducts, and other features and a minimum of 150 mm (6”) clearance between the old and new ceilings if you are dropping a ceiling.
Make sure there is a minimum of 50 mm clearance from any pipes, wires and other objects that could interfere with placement of the Ceiling tile.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What can be used to temporarily hold ceiling components together before fastening?

A

Ceiling track clips

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Steel door frames that are part of a block wall are kept from bowing or twisting by using what?

A

Using internal spreaders the size of the door plus clearances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Where is the chalk line reference required for ceiling tile wall mouldings?

A

The chalk line is snapped at the top of the wall moulding so not visible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What supports the main tees?

A

Hanger wires which are suspended from eye tees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the length required for border tees in a grid ceiling system?

A

The length of the border tee will equal the measurement from the last tee to the wall angle minus 3 mm for the wall angle thickness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is an example of a semi-concealed suspended ceiling?

A

H and T. Only the main runners (H) are visible from below on the finished surface.

17
Q

What spacing is necessary for the concealed system furring bars?

A

Spaced a maximum of 600 mm o.c. and within 150 mm of walls. 25 mm clearance between furring ends and abutting walls or partitions.

18
Q

What bracing is required for a metal frame that will be in a concrete block wall?

A

Sufficient to keep the frame level and plumb in two directions.