02. Remedies. Flashcards
Damages are usually intended …
to put the contracting parties in the position they would have been had the contract been performed.
Alternative dispute resolution.
Processes such as negotiation, arbitration, mediation, ajudication or expert determination intended to avoid the expense of court hearings.
Processes such as negotiation, arbitration, mediation, ajudication or expert determination intended to avoid the expense of court hearings.
Alternative dispute resolution.
If … are an adequate remedy then …. will be awarded.
damages
Equitable remedies may only be awarded …
at the discretion of the court.
Issues regarding a claim for damages: R* (AN, ItCoBP), M (EI / RI), MD?, MoL?
remoteness of damage
Issues regarding a claim for damages: R (AN*, ItCoBP), M (EI / RI), MD?, MoL?
arising naturally from the breach
Issues regarding a claim for damages: R (AN, ItCoBP*), M (EI / RI), MD?, MoL?
in the contemplation of BOTH parties
Issues regarding a claim for damages: R (AN, ItCoBP), M* (EI / RI), MD?, MoL?
measure
Issues regarding a claim for damages: R (AN, ItCoBP), M (EI* / RI), MD?, MoL?
expectation interest
Issues regarding a claim for damages: R (AN, ItCoBP), M (EI / RI*), MD?, MoL?
reliance interest
Issues regarding a claim for damages: R (AN, ItCoBP), M (EI / RI), MD?*, MoL?
mental distress
Issues regarding a claim for damages: R (AN, ItCoBP), M (EI / RI), MD?, MoL?*
mitigation of loss
Breaking the chain of causation.
Establishing that damage is too remote from a breach of contract to be claimable.
Establishing that damage is too remote from a breach of contract to be claimable.
Breaking the chain of causation.
If damage is neither a natural consequence of breach nor in the reasonable contemplation of both parties, including a mill being out of action due to a delay in the transportation of a mill shaft …
then it is too remote to be claimable.
The chain of causation has been broken.
If a claimant is unaware of a breach of contract, including a synthetic fibre plant supplied with contaminated butane gas, …
only subsequent recklessness may beak the chain of causation.
If losses are exceptional or abnormal, including the loss of dyeing contracts due to the late installation of a boiler, …
then they are only claimable if the breaching party knew of their existence.
A party suffering a breach of contract is required to … their losses.
mitigate
Damages sufficient to satisfy the expectation interest of an injured party are those required to …
put them in the position they would have been had the contract been performed.
Damages sufficient to satisfy the … interest of an injured party are those required to put them in the position they would have been had the contract been performed.
expectation
Damages sufficient to satisfy the reliance interest of an injured party are those required to …
put them in the position they would have been had they not relied upon the contract.
Damages sufficient to satisfy the … interest of an injured party are those required to put them in the position they would have been had they not relied upon the contract.
reliance
Speculative profits, including those from the production of a TV film, …
will not be awarded as damages.
Reliance cases are usually claims for …
wasted expenditure.