02 Key Issue 1 Flashcards
What caused the drain to become defective?
This was unconfirmed as the excavations were not undertaken in the end, however I suspected it may have been a combination of extra load due to recent resurfacing of the area and roots from adjacent trees attacking the displaced joints
What tests could you have undertaken to determine whether the drain was defective?
- Visual inspection - lift inspection chamber cover and flush/run water to observe flow
- Water test - insert bung into one end of the pipe run and fill up pipe to a certain level, observing whether the level reduces (thus indicating pipe is leaking)
- Air test - bungs are placed at either end of a pipe branch (one connected to a pump), air is pumped into the pipe and the pressure monitored over a period of time to determine its watertightness
What impact could the defective drain have had on the existing building?
Any change in ground water levels as a result of a leaking drain may have undermined the building’s foundations, however there was no evidence of movement in this case
Did you need to consider any surrounding buildings before undertaking the excavations?
Had there have been any buildings within a closer proximity, I would have considered issuing a Notice of Adjacent Excavation under the Party Wall etc Act, however there were no structures within the required distance for such provisions to apply
Would a building surveyor design drainage?
They can do, however they may seek further advice from a structural engineer or specialist drainage contractor
Do you feel you are capable of assessing and designing drainage?
As the works in this case were localised and minor in complexity, I felt competent in its design by considering the appropriate guidance
How did you design the drainage?
- Mainly using Approved Document H (Drainage and Waste Disposal) as a guide and the relevant British Standards it relates to
- I also used information from the CCTV survey report to identify the location and extent of the works that required designing
- For option 2, I also used BS EN 12056 to calculate the flow rate and therefore gradient required for the above ground drainage pipework
What type of pipe was replaced and what did you replace it with?
The existing drain was vitrified clay pipework and I proposed the replace the defective section with clay pipe to match
How would the new underground pipe have been connected to the existing pipe?
I specified the installation of adjustable couplings that contained adjustable collars at each end made from a durable rubber material that could be tightened by stainless steel ‘jubilee clips’ to connect the two sections of pipe in a line
How did you specify the new build-up of the ground from the drainage to the surface?
I looked in Approved Document H and as I was specifying rigid pipework, it had to sit on 100mm of granular material (graded 5-10mm) up to half the depth of the pipe and then selected fill (free from stones >40mm and lumps of clay >100mm) 150mm above the top of the pipe, with the rest of the excavation backfilled as normal
Does the bedding that sits around the underground drain need to be compacted?
Yes, a maximum compaction fraction of 0.3 was detailed in Approved Document H
Was the defective pipe for foul water or surface water and why would this have an impact?
It was a combined drainage system receiving both foul and surface water, which may have had an impact when specifying the size of the pipework, however this was not a factor for this minor like-for-like repair
In option 2, how would you have connected the new above ground drain to the existing SVP?
A section of the existing SVP would have been removed and replaced with a branch junction connector, providing a ‘T’ junction for the new pipework, all connected with adjustable couplings
In option 2, to enable you to install more than one toilet, why could you not have used a shallower gradient?
- Using BS 12056, I calculated the flow rate of the new toilet and used this with Approved Document H to determine the required gradient
- As the flow rate would have been less than 1 l/s (even with 2 toilets installed), a 1:40 gradient was required
- I also spoke to a building control officer, who advised that due to the predicted low useage of the area, no less than a 1:40 gradient would have been suitable
In option 2, what other options did you consider to allow for the installation of more than one toilet?
- I considered the use of a macerator pump, however the client was strongly against this due to previous maintenance issues on other projects as well as the amount of noise they generate
- I also considered ramping up to the area to allow a greater fall, however this was not practical due to the space restrictions