商务英语 Flashcards
Advance Payment
预付款
Certificated Value
已批复工程款
Deduct AP
预付款扣回
Deduct Retention Money
质保金扣留
Other Deductios
其他扣除项
Approved Payment Excluding VAT
不含税金额
Deduct PPH
预扣税(3%)
Total Certified
业主实际应付结算金额
Payment Due
应支付申请结算金额
Construction Dept
工程部
Commercial Dept
商务部
Reviewed&Approved
审核&批复
Preliminary Items
项目前期工作
Site work completion of Soil investigation&topography survey
完成土壤调查和地形测量的现场工作
Completion of detailed design for causeway&pond embankment
完成堤坝和池塘堤坝的详细设计
access bridge
引桥
jetty platform
码头平台
dredging
疏浚
Mobilization for dregding vessel&equipment
疏浚船机设备调遣
Piling barge
打桩船
Trench excavation for causeway
引堤基础挖泥
harbour&channel
港池航道疏浚
Sewage proof curtain
防污帘
Pond Embankment
围堰
Causeway
引堤
backfilling
回填
PHC pile
PHC钢管桩
driving pile
打桩
Precast beam
预制梁
cast-in-site concrete beam
现浇混凝土梁
installation of precast beam
预制梁安装
Handrail
栏杆
Procurement
采购
core concrete pouring of pile head
桩芯混凝土
precast member of superstructure
上层建筑的预制构件
cast-in place slab
现浇板