Facilitated workshops, group creativity technology, and group decision making technology are all tools associated with what?

A

Collect requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Name the one verify scope tool

A

Inspection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In addition to the requirements documentation, what other 2 outputs are associated with collect requirements?

A

Requirements traceability matrix

Requirements management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define scope occurs before and after what?

A

Occurs after collect requirements and before WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In addition to expert judgement what are the other 3 tools for Define Scope?

A
  1. Product analysis
  2. Alternatives identification
  3. Facilitated workshops
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 2 outputs of Define Scope

A
  1. Project scope statement

2. Project document updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Collect requirements takes place before and after what?

A

Before define scope, after identify stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is decomposition a tool of during scope management?

A

Create work breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 3 inputs to create WBS

A

Project scope statement
Requirements documentation
Organizational process assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is verify scope?

A

Verifying the product, service,or result of the project matches the documented scope.

NOT: seeing if the process is documented properly, instead verifying that the overall output is what was documented that its supposed to be.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the 4 outputs to create WBS

A

WBS
WBS dictionary
Scope baseline
Project document updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the things included in the project scope statement?

A

Many details pertaining to project and product deliverables:

  1. Goals
  2. Product description
  3. Requirements for the project
  4. Constraints and assumptions
  5. Identified risks related to scope
  6. Objective criteria for accepting product
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the inputs to verify scope

A

PM plan
Requirements documentation
Requirements traceability matrix
Validated deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the outputs of verify scope?

A

Accepted deliverables
Change requests
Project document updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the only tool for control scope?

A

Variance analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project goals, descriptions, requirements, constraints, assumptions, and identified risks, acceptance criteria are all likely inclusions in what key document?

A

Project scope statement

16
Q

Project scope statement…during scope management …what is it, what is an output of, what is it an input of

A

It is used to outline details related to the project and its deliverables
Output of: define scope
Input of: WBS

17
Q

What are organizational process assets?

A

Information, tools, documents, knowledge that organization possesses that could help you plan for your project

18
Q

What are enterprise environmental factors

A

Things that impact your project that are not part of the project itself.

19
Q

What are the 5 processes in scope management

A
Collect requirements
Define scope
Create WBS
Verify scope
Control scope
20
Q

What are the 4 inputs for control scope

A

PM plan
Work performance information
Requirements documentation
Requirements traceability matrix