Work Flashcards
Facilitated workshops, group creativity technology, and group decision making technology are all tools associated with what?
Collect requirements
Name the one verify scope tool
Inspection
In addition to the requirements documentation, what other 2 outputs are associated with collect requirements?
Requirements traceability matrix
Requirements management plan
Define scope occurs before and after what?
Occurs after collect requirements and before WBS
In addition to expert judgement what are the other 3 tools for Define Scope?
- Product analysis
- Alternatives identification
- Facilitated workshops
What are the 2 outputs of Define Scope
- Project scope statement
2. Project document updates
Collect requirements takes place before and after what?
Before define scope, after identify stakeholders
What is decomposition a tool of during scope management?
Create work breakdown structure
What are the 3 inputs to create WBS
Project scope statement
Requirements documentation
Organizational process assets
What is verify scope?
Verifying the product, service,or result of the project matches the documented scope.
NOT: seeing if the process is documented properly, instead verifying that the overall output is what was documented that its supposed to be.
What are the 4 outputs to create WBS
WBS
WBS dictionary
Scope baseline
Project document updates
What are the things included in the project scope statement?
Many details pertaining to project and product deliverables:
- Goals
- Product description
- Requirements for the project
- Constraints and assumptions
- Identified risks related to scope
- Objective criteria for accepting product
What are the inputs to verify scope
PM plan
Requirements documentation
Requirements traceability matrix
Validated deliverables
What are the outputs of verify scope?
Accepted deliverables
Change requests
Project document updates
What is the only tool for control scope?
Variance analysis
Project goals, descriptions, requirements, constraints, assumptions, and identified risks, acceptance criteria are all likely inclusions in what key document?
Project scope statement
Project scope statement…during scope management …what is it, what is an output of, what is it an input of
It is used to outline details related to the project and its deliverables
Output of: define scope
Input of: WBS
What are organizational process assets?
Information, tools, documents, knowledge that organization possesses that could help you plan for your project
What are enterprise environmental factors
Things that impact your project that are not part of the project itself.
What are the 5 processes in scope management
Collect requirements Define scope Create WBS Verify scope Control scope
What are the 4 inputs for control scope
PM plan
Work performance information
Requirements documentation
Requirements traceability matrix