1
Q

Overall responsibility for compliance with API 653

A

1.2
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Perform FFS evaluations on corroded tank shells

A

4.3.1.2
E

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In a shell LTA, find t2 (thinnest area exclusive of pit)

A

4.3.2.1.a
I

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In shell LTA, determine placement of vertical lines (L) for Corr Ave.

A

4.3.2.1.c
I

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Determine MFL Threshold

A

4.4.5.1 Note 1
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Perform the Routine In-Service Inspection

A

6.3.1.1
Ops

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Perform the External Inspection

A

6.3.2.1
I

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Determine the extent of UT measurements on the shell

A

6.3.3.1
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Review the results of CP surveys

A

6.3.4.1
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Assure competency of personnel performing CP surveys

A

6.3.4.2
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Choose to use RBI to set Internal Interval

A

6.4.2.2.2
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Perform the Internal Inspection

A

6.4.1.2
I

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Conduct an RBI assessment

A

6.4.2.2.2
RBI Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Review and approve RBI reassessments every 10 years

A

6.4.2.2.2
RBI Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Approve Standard Deferral for Internal Inspection

A

6.4.3.1
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Written request for a Std Deferral of Internal Inspection

A

6.4.3.1.e
I & O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Provide written reasons for a Standard Deferral for Internal Insp

A

6.4.3.1.i
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Determine if Risk is okay for a Risk-based Deferral for Internal Insp

A

6.4.3.2
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Maintain tank records

A

6.8.1
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Prepare report after each External & Internal Inspection

A

6.9.1
I

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Maintain inspection reports & recommendations for life of tank

A

6.9.1
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Review inspection findings and recommendations

A

6.9.3.2
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Written approval to delay/delete recommended repairs or monitoring

A

6.9.3.2
O

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Evaluate and accept NDE examination results

25
Q

Authorize all alterations

A

9.1.4.a.1
E

26
Q

Authorize all repairs that require a hydrotest

A

9.1.4.a.2
E

27
Q

Authorize repairs that do not require a hydrotest

A

9.1.4.b
I Or E

28
Q

Designate inspection hold points for repairs & alterations

A

9.1.5.a
I Or E

29
Q

Specify min documentation to be submitted after repairs & alterations

A

9.1.5.b
I Or E

30
Q

During repairs & alteration, Approve proposed design, mtls, WPSs, etc

A

9.1.6
I Or E

31
Q

Approve all repair, alteration and reconstruction work at hold points

A

9.1.6 & 10.1.4
I Or E

32
Q

Approve all repair, alteration & reconstruction work at completion

A

9.1.6 & 10.1.4
I Or E

33
Q

Design door sheets that differ from API 653 designs

34
Q

Approves in-writing, door sheet designs that differ from API 653

35
Q

Allow lap-patch repairs to used on tank shells

36
Q

Determine life of nonmetallic repairs

37
Q

Evaluated whether nonmetallic repair restores needed hoop strength

A

9.4
E & O & Composite Manufacturer

38
Q

Review & approve the use of non-code specified lap patches on bottom

39
Q

Approve lap patch in critical zone if bottom thickness is < 0.100”

A

9.11.1.6.b
E

40
Q

Run the hot tap machine

A

9.15.5.4
Qualified Operator

41
Q

Authorize all reconstruction work

A

10.1.3
I or E

42
Q

Designate inspection hold points for reconstruction

43
Q

Specify min documentation to be submitted after reconstruction

44
Q

Access to Repair Org’s welding records

A

11.2.1
I or O

45
Q

Review the use of Preheat or Controlled Deposition welding in lieu of PWHT

46
Q

Concur in writing use PWHT alternative for matl’s of unknown toughness

47
Q

Approve the use of friction stud welding

A

11.5
O & Repair Org

48
Q

Review & approve exempting a hydro after a major repair or alteration

A

12.3.3.2
E & O

49
Q

Authorize FFS evaluation to exempt a hydro after repair

50
Q

Perform FFS evaluation to exempt a hydro after repair

51
Q

Request nameplate for existing tank without a nameplate

52
Q

Tank w/o nameplate, oversee attachment of new nameplate

A

13.1.2.2/3
I

53
Q

Perform tank settlement survey

A

B.2.1
Experienced Person

54
Q

Do rigorous stress analysis for floor settlement exceeding 653 limits

A

B.3.2/3.2.4
E

55
Q

Floor scan qualifications – Decide to use Annex G or modify Annex G

56
Q

Verify if floor scans are following the examination procedure

A

G.3.1
I or O

57
Q

Perform qualification tests for floor scanning examiners

A

G.4.6
O or 3rd Party

58
Q

Perform Similar Service assessments

A

H.1
I or E or Knowledgeable One

59
Q

Authorize use of non-metallic repairs