Week 5 - Project Management 2 Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

What questions should be considered in risk management?

A

What is likely to happen?
What can minimise the probability or impact of these events?
What cues will signal the need for action?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is risk management defined as?

A

The art of identifying, analysing and responding to risk factors throughout the life of a project and in the best interest of its objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is project risk defined as?

A

An uncertain event or condition that if occurs may have a positive or negative effect on project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are common types of project risk?

A
Absenteeism
Resignation
Staff pulling away
Time overruns
Unavailable skills or poor training
Incomplete specs
Change of orders
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a risk impact matrix?

A

It is a way of measuring risk, measuring the consequences and likelihood

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are some risk mitigation strategies?

A

Accept, minimise, share, transfer, contingency reserves, insurance, workaround, mentoring, cross training

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does control and documentation do?

A

Helps managers classify and codify risks, responses and outcomes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are some common sources of project cost?

A

Labour, materials, subcontractors, equipment and facilities, travel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are some problems with cost estimation?

A

Low estimates, unexpected difficulties, lack of definition, spec changes, external factors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is contingency funding?

A

It is where funds are set aside for future unknowns, in case something unexpected happens

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the benefits of contingency funding?

A

Recognises future unknowns, adds provision for plans for an increase in project cost, acts as warning signal to overdrawn budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does project scheduling require you to do?

A

Follow some laid-out steps in order to allow a schedule to take shape

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is project planning defined as?

A

The identification of the project objectives and the ordered activity necessary to complete the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a project network diagram?

A

Any schematic display of the logical relationships of project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is an early start date in project scheduling?

A

The earliest possible date an uncompleted activity can start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a late start date in project scheduling?

A

The latest possible date that an activity may begin without delaying a milestone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is calculated in the forward pass of a project scheduling diagram?

A

Earliest start / earliest finish of an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is calculated in the backward pass of a project scheduling diagram?

A

The late start / late finish data for a task in the network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the float in a Project Network Diagram?

A

The amount of time an activity may be delayed from its early start without delaying the finish of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is the critical path in a project network diagram?

A

The path through the project network with the longest duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the critical path method?

A

A network analysis technique used to determine the amount of schedule flexibility used to determine the minimum project duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What does m, b and a stand for in beta distribution?

A
most likely (m)
most pessimistic (b)
most optimistic (a)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the formula for activity duration?

A

(a + 4m + b) / 6

where a is most optimistic, b is most pessimistic and m is most likely

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is the formula for calculating activity variance?

A

((b - a) / 6) ^ 2

where a is most optimistic, b is most pessimistic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What are some ways of reducing a critical path?

A

Eliminate tasks on the path, plan serial tasks in parallel, overlap sequential tasks, shorten task duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is a Gantt chart?

A

A time phased network tracking tool

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What are some benefits of Gantt charts?

A
Easy to comprehend
They identify the schedule baseline network
Allow for updating and control
Identify resource needs
Easy to create
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What is the project control cycle?

A

Setting a goal
Measuring progress
Comparing actual with planned
Taking action, recycling the process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What are milestones?

A

These are events or stages of a project that represent a significant accomplishment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What do milestones do?

A
Signal completion of important steps
Motivate team
Offer re-evaluation points
Coordinate schedules
Identify review gates
Signal when work should start
Delineate work packages
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is Agile Project Management (Agile PM)

A

A new era in project planning that places a premium on flexibility and evolving customer requirements throughout the development process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What are some features of Agile PM?

A

You plan the work, then work the plan
Customer needs may evolve over the project
Importance of involving customer leads to incremental, iterative planning process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What are some unique features of Agile PM?

A

Recognises mistake of assuming once the initial project is planned, the project will be executed to original specs.
It is flexible - iterative system for managing projects with change and uncertainty
It is a rolling wave of continuous plan - execute - evaluate cycle
Emphasis on adaptation, flexibility, coordinated efforts of multiple disciplines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What is Agile PM often referred to as?

A

Scrum

35
Q

What is a sprint in Agile PM?

A

One iteration of the agile planning and executing cycle

36
Q

What are the stages in the agile cycle?

A

Plan-Execute-Evaluate

37
Q

What is the meaning of scrum in Agile PM?

A

The development strategy agreed to by all key members of the project

38
Q

What is time-box in Agile PM?

A

The length of any particular sprint, fixed in advance, during the scrum meeting

39
Q

What is a user story?

A

A short explanation of the ned user that captures what they do or need from the project

40
Q

What is a scrum master?

A

This is the person on the project team that is responsible for moving the project forward between iterations, removing impediments and solving disputes

41
Q

What is the sprint backlog?

A

Backlog of items selected for the sprint and a plan for delivering the sprint goal

42
Q

What is the burndown chart?

A

The remaining work in the sprint backlog

43
Q

What is the product backlog?

A

This is a prioritised list of everything that might be needed in the completed product and source of requirements for any changes

44
Q

What is the work backlog?

A

An evolving, prioritised queue of business and technical functionality that needs to be developed into a system

45
Q

What are stages in a sprint?

A
Sprint planning
Daily scrums
Development work
Sprint review
Sprint retrospective
46
Q

What are some problems with agile?

A

Requires active user involvement
Scope creep
Hard to predict end product at the start
Requirements are kept to a minimum, so can lead to confusion
Testing is integrated throughout lifecycle - adds cost
Burden of frequent delivery
If misapplied, expensive with few benefits

47
Q

What is a retrospective?

A

It is a time where a team stops to reflect on how to become more effective - and then adjusting their behaviour accordingly

48
Q

What is said about learning from experience?

A

Is that it is not automatic

49
Q

What do retrospectives create?

A

The opportunity for participants to learn improvement

The opportunity to harvest the experience of the team

50
Q

Why should you look back in regards to project retrospectives?

A
Identify needs for improvement
Builds motivation for change
Team actually designs the change
Can help build alliances when there are multiple teams
Offers closure (from bad experiences)
51
Q

Who designs the changes in regards to project retrospectives?

A

The team that was involved!

52
Q

Why do the team design the changes in regards to project retrospectives?

A

They are in the best position to identify, organise and prioritise problems.
Owning the changes means the team is the master of its process

53
Q

What do retrospectives provide in failed projects?

A
Opportunity to learn from failure
A focus on improvement rather than blame
Close the door against similar adversity
Learning, growth, maturity
Experiences recalled help foster teams common focus
54
Q

What are retrospectives never about?

A

Blaming, naming or shaming

55
Q

Who is involved in retrospectives?

A

The team and scrum master must be invovled, it is good to involve external team members

56
Q

Who is never involved in a project retrospective?

A

The customer and management

57
Q

Who does a retrospective facilitate?

A

Professionals, scrum master, any team member

58
Q

What do we look for in retrospectives?

A

What went well (celebrate, recognise heroes, share good practice)
What did not go well (what to avoid, how to work differently)
What are we still puzzled about?

59
Q

When are retrospectives carried out?

A

At the end of the project
During the project:
- the end of each sprint (find out what we can put in the next sprint)
- at specified milestones
- after a project surprise (reactive retrospective)

60
Q

What are some goals of retrospectives?

A
Capture effort data
Get the story out
Improve process, procedures, management and culture
Capture collective wisdom
Repair any damage to the team
Enjoy the accomplishment!
61
Q

What is the structure of a retrospective?

A
Set the stage
Gather the data
Generate insights
Decide what to do
Close the retrospective
62
Q

What are some possible tools for retrospectives?

A

Fishbone diagrams, Pareto charts

63
Q

What do insights allow?

A

The team to step back, identify the bigger picture, grasp root causes.

64
Q

What emerges once insights have been gained?

A

The solutions

65
Q

When generating insights, what do we interpret?

A

Causes, effects, strengths and weaknesses

66
Q

How can we map stakeholders?

A

By using a matrix showing their level of attention and their power

67
Q

What is the problem with agile and the iron triangle?

A

Project management cannot be agile and fit within the iron traingle objectives without careful recognition of risks

68
Q

In what environments does agile work better within?

A

Low risk environments - you wouldn’t agile a plane!

69
Q

Where does a customer sit in the stakeholder matrix?

A

High attention and high power

70
Q

What do you need to do with customers?

A

Actively cultivate them

71
Q

How can project risks be mitigated?

A

Through the management of customer expectations

72
Q

How can project management risks be mitigated by management customer expectations?

A

Clarifying design limits, scope within budget, agreeing feasible and realistic goals, corroborating facts before starting

73
Q

Why should you work with the customer to establish facts?

A

Keeps them informed with cost/time/scope

Communicates design limits and allows for a safe and effective implementation

74
Q

What type of design should be made when working with the customer?

A

A feasible one that is an acceptable one

75
Q

How can customer expectations be met?

A

The 7Cs

76
Q

What are the 7Cs?

A
Client
Clarity
Create
Change
Confirm
Continue
Close
77
Q

What does Client mean in the 7Cs?

A

Use expertise and experience to win the business

78
Q

What does Clarity mean in the 7Cs?

A

Understand the customer needs through meetings, interviews…

79
Q

What does Create mean in the 7Cs?

A

Scope and agree design specifications

80
Q

What does Change mean in the 7Cs?

A

Manage and implement the project

81
Q

What does Confirm mean in the 7Cs?

A

Clarify the project success

82
Q

What does Continue mean in the 7Cs?

A

Establish and implement post-project support

83
Q

What does Close mean in the 7Cs?

A

Maintain customer relationships for testimonials and winning of future projects