week 5 Flashcards

1
Q

Six Types of Construction Drawings`

A
PASMCES
plumbing 
architectural 
structural 
mechanical
civil
engineering
sometimes fire protection
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

explain cival

A

Used for work that has to do with construction in or on the earth.
AKA: Site plans, survey plans, or plot plans
Show the location of the building on the site from an aerial view.
Shows natural contours of the earth.
THIS IS WHERE IT ALL STARTS! IF THE SITE IS NOT ACCEPTABLE, THERE IS NO REASON TO CONTINUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

explain architectural plans

A

Show the design of the project
One part is the floor plan.
Any drawing made looking down on an object is commonly called a plan view.
Floor plan is an aerial view of the layout of each room.
Provides the most information about the project.

Roof Plan
View of the roof from above.
Shows the shape of the roof
Elevation drawings are side views.
Show height
Section drawings-show how the structure is to be built
Cross-sectional views that show the inside of an object or building
Show the construction materials to use and how the parts of the building fit together.
Detail drawings-enlarged view of some special features.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

explain structural plans

A

A set of engineered drawings used to support the architectural design.
Includes general notes which give details of materials to be used.
Includes a foundation plan
Shows the lowest level of the building, including concrete footings, slabs, and foundation walls.
Shows the materials to be used for the walls, whether concrete or masonry, and whether the framing is wood or steel.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

explain mechanical plans

A

Engineered plans for motors, pumps, piping systems, and piping equipment.
HVAC(heating, ventilating, and air conditioning) plan is included in mechanical plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

explain plumbing plans

A

Show the layout for the plumbing system that supplies the hot and cold water, for the sewage disposal system, and for the location of plumbing fixtures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

explain electrical plans

A

Drawings for electrical supply an distribution
May appear on the floor plan for simple construction projects
Can include lighting plans, power plans, and panel schedules.

Fire Protection Plans
Show the piping, valves, heads, and switches that make up a building’s fire sprinkler system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what is the developers equatoin

A

V = L + B + F + P

Where:
V = Value of development
L = Land costs and expenses
B = Building costs
F = Finance costs
P = Profit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

3 cost estimating techniques

A

Superficial area
Elemental cost
Quantity surveyor’s approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

explain superfical approaches + issues

A

Involves calculating an appropriate all-in cost that will approximate to the total cost of the development of all components of the building.
E.g. Built Area 800sqm multiplied by construction cost $1,000/sqm + 5% inflation allowance = $1,050/sqm which equates to $840,000.

Issues
Every project is different – buildings are not mass produced widgets
Individually built and tailored to meet differing requirements – characteristics and conditions (ground conditions, access, machine requirements, market conditions)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

explain elemental cost approach

A

Estimation of building cost but provides more detail thus achieving greater accuracy.
This method requires the built elements of the building to be divided into elemental components for more accurate cost estimation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

advantages of elemental estimating method

A

An elemental cost analysis is easy to understand .It makes sense to people involved in the project because it shows the cost breakdown by building elements.
Elements taking up the biggest cost are easily identified and can be adjusted as required.
The quantity surveyor is able to check the elemental costs throughout the design stage, which makes it a more reliable estimate than the superficial area method.
Because all the main elements of a building are analyzed, and linked to BOQ (bill of quanities) items, this estimate is much more closer to the tender value than the superficial area method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

disadvantages of elemental method of estimating

A

Plan adjustments and constant cost checking in the preliminary stage takes a lot of the Architect’s and Quantity Surveyor’s time.

The Architect and QS involved in the preliminary stage need to be well versed with the cost implications of design specifications i.e. building materials, construction technology, plan shape etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

explain quantity surveyor approach

A

This is the most detailed and the most accurate approach.
It requires the building to be broken down into its building components, each being accurately measured and estimated, with accurate costs per unit attached to each.
Issues:
Not a practical approach for someone who is NOT a QS
Requires detailed information about the property/project to justify the use of this method
Usually requires a Quantity Surveyor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what may other costs include

A

Professional fees
Exclusive of the cost of employing professional team
Costs are not fixed and will commonly vary depending on project size, scope, complexity, relationship and negotiation.
Complexity of project will change the profile of fees

Contingency
Construction contingency – allowance for risk in the construction
Foundation contingency
Other contingency – unforseen events, changing ground conditions, adverse weather, impact of design changes etc.

Rise and Fall
Inflation, cost increases etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What do we use to calculate costs

A

You have two options in feasibility studies

Use a Quantity Surveyor (QS) (expensive at this stage of the process)

Use Rawlinsons (or other cost information) to work out the cost of the project based on an average to use in your project.

17
Q

4 key areas of rawlingson cost estimations

A

Based on GFA (Gross Floor Area)

  1. Estimating
  2. Estimating Elemental Costs
  3. Estimating Comparatrive Costs
  4. Detailed Costs

Note Rawlinsons does not include;
Land
Demolition
GST

18
Q

explain rawlinson’s - estimating

A
  1. Estimating
    Building costs per square meter
    Categorised by building type
    Separated by different locations (by state)
19
Q

explain rawlinson’s estmating elemental costs

A
  1. Estimating Elemental Costs
    Breakdown of the building
    Elemental costs provides a more detailed analysis of the breakdown of the building costs
    Allows for greater tailoring of costs, for example, if the foundations are going to be more significant than the average building of that type then it becomes easier as the cost of split to adapt and increase the costs
20
Q

explain rawlinson’s estimating comparative costs

A
  1. Estimating Comparative Costs
    More detail but still covers on a average based on the purpose/ use. Uses products/ parts
    Useful for putting in more detail or varying details
    E.g. Building a commercial office building and want to upgrade the level of finishes. Average costs for better finishes can be obtained here.
21
Q

explain rawlinson’s - detalied costs

A

. Detailed Costs
Most complex
Done by trade rather then by product/ part
Have to work everything out!
This is essentially the territory of the QS

22
Q

what is LCC

A

Methodology to determine the most cost-effective option among different alternatives to purchase, own, operate, maintain, and dispose of a building or building system over its entire lifetime
It was developed to take into account both capital and running costs when considering the design of buildings
Useful to compare project alternatives that are technically acceptable, but differ with respect to initial costs and operating costs
Allows an investor to calculate all project costs and compare cost effectiveness of alternative investment options

23
Q

types of life cycle costs

A
Initial costs
Purchase
Acquisition
Construction
Installation
Replacement costs
Residual values
Resale
Salvage values
Disposal costs
Operation, maintenance, and repair costs
Utility costs
Costs are only considered if they are relevant and significant
24
Q

STEPS in peforming LCCA

A

Identify alternatives
Specify data requirements and establish assumptions
Estimate costs and adjust for time value of money
Calculate total LCC for each alternative

85% of a Facility’s Total Cost is in Operations and Maintenance