Week 4- Project Crashing and Gantt Charts Flashcards
how can a project be completed sooner?
By “crashing” the time it takes to complete certain stages by throwing more money at it
What impact does project crashing have on indirect and direct costs?
Increases direct costs but may decrease indirect costs because you may avoid the pitfalls of finishing the project late
What is the formula to work out the cost to crash per period?
Cost cost- Normal cost/ Normal time- crash time
What is the crash cost?
The activity cost associated with the crash time
what is the crash time?
The shortest possible tie to complete an activity
what is the first tihing you should do when crashing a project?
Work out the cost to crash per period for each activity in the project
What are the only activities that you can crash to reduce the length of the project?
Ones on the critical path
which activity are you going to crash first?
The one on the critical path with the lowest cost of crashing per period
When should you stop the crashing proceedure?
- When the target project completion is met
- The completion date cant be shortened any further
- An increase in direct costs exceeds the savings from indirect costs
what are gantt charts used for?
Communicating project plans to stakeholders
which activities should you plot on a gantt chart first?
The critical ones
what re the two extemes at which you can plot non-critical activities?
They can be plotted for completion as early as possible or as late as possibel
what is the reason for plotting a non critical activity as early as possible on a gantt chart?
If there is a high risk of not completing them on time in order to minimise the risk of the project running over schedule
what is the reason for plotting a non critical activity as late as possible on a gantt chart?
If you have a loan and dont want to start paying interest on the machinery until the last possible point (pushing costs into the future to maintain cash flow)
what are the advantages of a gantt chart?
- Easily understood
- easily linked to a precedence table so can be quickly plotted