What is the power leg voltage in a 120/240 3ph service?
208 volts
WYE or DELTA? 120/208
3 ph service
WYE
In a WYE-WYE bank, what must be done to the H2s on each transformer?
Tie them together and connect to neutral
In a WYE-WYE bank, why is it important to parallel the secondary windings?
To get the full kVA rating from the transformer
What is the hot-leg-to-hot-leg voltage (p-p) in a standard 120/208 3ph service?
208 volts
How many “power” transformers are there in a closed-DELTA bank?
2
What must be done to the secondary coils in a DELTA-WYE bank?
They must be paralleled; AC-BD
In a 240 3ph-3wire service, what happens if one phase gets grounded?
Nothing. It becomes a corner ground, and the 3-phase service is still delivered. You can ground one time at any point in the service.
WYE or DELTA? 240/480
3 ph service
DELTA
What is the power-leg-to-hot-leg voltage in a 120/240 3ph service?
240 volts
What does “Alley-Cat, Bad-Dog” mean?
When paralleling the windings for a WYE secondary, open the lid and connect A and C together to X1, and then B and D together to X2.
WYE or DELTA? 277/480 3 ph service
WYE
In a WYE-WYE bank, what must be done to the X2s on each transformer?
Tie them together and connect to neutral
In a WYE-DELTA bank, what must be done to the H2s on each transformer?
They must be tied together, but not grounded or connected to neutral