Week 3 Quiz Flashcards

1
Q

The structure that manages projects within the existing organisational structure is __________ organisation.

a. Weak matrix
b. Strong matrix
c. Project
d. Functional
e. Balanced matrix

A

Functional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

MegaComputers, Inc. has assigned a project manager for each of the five new-product teams. The managers as well as the project team members work on the projects on a full-time basis. The structure being used is ________ organisation.

a. Functional
b. Strong matrix
c. Project
d. Balanced matrix
e. Weak matrix

A

Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The structure in firms where projects are the dominant form of business is known as:

a. Balanced matrix organisation
b. Functional organisation
c. Strong matrix organisation
d. Projectised organisation
e. Weak matrix organisation

A

Projectised organisation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In which organisational form is it most difficult to integrate project activities?

a. Projectised
b. Strong matrix
c. Functional
d. Weak matrix

A

Functional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

In which organisational form would the project manager possess the greatest amount of authority?

a. Weak matrix
b. Projectised
c. Functional
d. Strong matrix

A

Projectised

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Matrix management violates the management principle of

a. Span of control
b. Empowerment
c. Unity of command
d. Parity principle

A

Unity of command

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Kim is reviewing a proposed project. The scope of the project is narrow with a lot of in-depth expertise required and it will take a short period of time to complete. The best choice for organising the project is ________ organisation.

a. Project
b. Strong matrix
c. Functional
d. Weak matrix
e. Balanced matrix

A

Functional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In which organisational form is the project manager least likely to share resources with other projects?

a. Strong matrix
b. Projectised
c. Weak matrix
d. Functional

A

Projectised

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which of the following is an advantage of a functional project management organisation?

a. Maximum flexibility in the use of staff
b. Shorter project duration
c. Strong motivation of project team members
d. Good integration across functional units

A

Maximum flexibility in the use of staff

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In which of the following is the balance of authority strongly in favor of the functional managers?

a. Balanced matrix
b. Weak matrix
c. Strong matrix
d. Strong

A

Weak matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly