Week 3 - Capital budgeting Flashcards

1
Q

What are the key questions for capital budgeting?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is cost of capital?

A
  • the minimum risk-adjusted return that a project (investment) must earn in order to be acceptable to the shareholders
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are to two types of projects?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the two types of Cash Flows?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the different evaluation techniques?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the Payback Period?

A
  • the number of years needed to recover the initial cost of investment
  • Its a type of break even assesment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Pros and cons for The payback Period?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the discounted payback period?

A

Same as payback period, but cash flows are discounted. (Essentially offsetting the time that the project has paid back)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is NPV?

  • when should you accept (reject) the project?
A
  • Sum of the PV of the CF, minus initial outlay/cost
  • NPV>0 –> accept
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the profitability index?

A

Sum of the present value of the CF divided by the initial costs

  • so instead of subtracting (as with the NPV), we divide by the costs

–> Essentially the same as NPV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the IRR?

A
  • IRR is the return on a firm’s invested capital over a period of time (n)
  • IRR is the discount rate that equates the PV of CF to the initial cost –> Alternatively, set NPV = 0.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When should a firm accept (reject) a project according to IRR?

A
  • IRR > k –> Accept

(k is the required rate of return - in other words ‘the cost of capital’).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

NPV vs. IRR?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Explain

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Strongest argument for choosing NPV over IRR?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the difference between Modified IRR and IRR?

A

MIRR assumes that CF are reinvested at the cost of capital (k) instead of at IRR

-

17
Q

When do we get multiple IRR?

and what is the relationship?

A
  • if the project has more than one sign change, then we get multiple IRR
  • for every change there is one IRR