Week 2 Flashcards
Definition of project cost estimation
The determination of probable costs of any given project where the estimate is prepared before the actual delivery of the project.
Purpose of project cost estimation
A forecast of all direct and indirect costs to complete a project (material, labour, equipment, and administrative costs).
What ways are there to estimate?
- Parametric estimating, first divide a project into units of
work. Then, determine the cost per unit, and then multiply the number of units by the cost per unit to estimate the
total cost. - First Principles is the process of building-up prices, or rates, for an item or piece of work considering all the parts and activities needed to put it together
Example of cost indices
■ General Building
■ Manufacturing
■ Power
■ Water Supply
■ Sewerage/Solid Waste
■ Industrial Process
■ Petroleum
■ Transportation
■ Hazardous Waste
First Principles Estimating factors.
– Waste
– Labour
– Productivity
– Financials
– Overheads
– Contingencies
– Risk
– Profit
Estimate Components - Accuracy factors.
■ Construction materials
■ Labour
■ Equipment
From the Estimate Components, what need to be considered for Construction Materials.
■ Quantity
■ Waste
■ Pricing
Equation for labour cost related.
■ Total cost of labour = Σ total work hour (i) * wage rate (i)
■ Total work hours = Σ quantity of work (i) / productivity rate (i)
Monetary factors
■ Base Wage rates
■ Fringe benefits (extra compensation companies give their employees)
■ Wage premiums
Factors that affect productivity
■ External factors (Market conditions and Environmental conditions)
■ Internal factors (Work conditions and Management conditions)
Direct vs. Indirect Costs
■ Direct Costs:
Material
Labour
Equipment
Subcontracted items
■ Indirect Costs:
Project Field Office
Laydown yard
Project Management
Accounting
Contingencies
■ Contingency is that amount of money added to an estimate to cover the unforeseen needs of the project, construction difficulties, or estimating accuracy.
8 Project Phases
1.Project Establishment
2.Concept Design
3.PreIiminary Design
4.Developed Design
5.Detailed Design
6.Procurement
7.Construction Admin
8.Post Completion
what is Concept Design and Financial Feasibility phase…
Identify a potentially beneficial business opportunity and perform initial analysis, scoping and Order of Magnitude Estimate to determine whether the opportunity is worth further investigation.
Definition of Historical Estimate
This type of estimate uses costs taken from a similar project done in the past. The price can be adjusted for inflation or any different
parameters attached to this particular project.
Preliminary Design Phase or Parametric Estimate….
Perform adequate conceptual design to allow selection of the best of identified project approaches, analyse concept(s) and prepare Cost Estimate to confirm project viability.
Examples of Detailed Design or Detailed Estimate
■ All design parameters are complete.
– CM of concrete, tons of structural steel, interior finishes specified
■ Perform Quantity Take-off of all design parameters (cost components of the project.
– Quantity Take-off - A detailed measurement of materials and labour needed to complete a construction project. These measurements are used to format a bid on the scope of construction.
■ Detailed Estimate performed from unit rates assigned to each quantity take-off of
materials (includes material, labour, equipment, and admin)
– $/m3 of In-situ Concrete
– $/m2 of Gyp Board
– $/m of Fence
■ Detailed Estimate: +/- 5 %
■ Bottom-Up Estimate
The project management structure consisted of…
■ Time
■ Resources
■ Scope
The project can be divided into activities
(WBS) for:
■ Cost estimation
■ Scheduling