week 10 - work systems Flashcards

1
Q

what is the cycle time (CT)?

A

> interval of time between the exit of 2 consecutive units at a stage , or at the end of a process

> CT = ST / nb of ressources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is the production rate (PR) of a workstation ?

A

> number of units produced per unit of time (1h)

> rate = 60 min / CT or 1h / CT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what is the difference between sequential VS parallel process?

A

sequential: process where work is divided in a series of specialized tasks

parallel: process where each employee realizes all task independently for the others

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what is the PR or a sequential process?

A

the PR of a sequential process is equal to the rate of the bottleneck

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is the PR of a parallel process (steps of calculations)

A
  1. sum of ST of each stations
  2. unit rate = 60 min / sum of ST
  3. total rate = nb of employees * unit rate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

formula of utilization rate of the workstation of a stage (sequential process)

A

utilization rate = CT of the stage / CT of bottleneck

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

formula for utilization rate of a worker

A

= (total ST - machine time) / total ST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly