Waterfall Planning Flashcards
1
Q
List the following processes in the order in which they should be completed
Create WBS
Collect Requirements
Plan Scope Management
Define Scope
A
- Plan Scope management
- Collect Requirements
- Define Scope
- Create WBS
2
Q
A Project ___________ meeting is a common practice to clearly communicate project objectives and build team and stakeholders buy-in
A
Kick-Off
3
Q
What is the major output created by the four scope management processes in the Planning Process Group
A
Scope Baseline