An operator should have an opportunity to review the lift station design in the following stages like planning stage, ____% design review, ____% design review, and ____% design review.
20%
40%
90%
The appropriate time to to develop and record both routine and emergency information and procedures for a new lift station is when?
Preliminary inspection
Lift station operation under test conditions will reveal only the ____________ equipment and construction problems.
Immediate
Official acceptance of completed corrective work for a lift station is the ______________ job.
Engineer’s
Mark each piece of lift station equipment with an identification code number and record the number and keep a minimum of ___ copies of this information.
2
When a new lift station is put in, it should be put on the preventative maintenance schedule when?
Right away
If the wet well is to be entered, all __________ _________ entry procedures must be followed.
Confined space
Before entering a wet well, you set up a blower that will give a minimum of _____ air changes a minute within the wet well.
2
If all conditions are satisfactory, then and only then is it permissible to ________ the wet well.
Enter
When stopping a lift station pump you hear a ratcheting sound. That is what engaging?
Backspin preventer
Low head conditions in pumps can be temporarily solved by throttling a discharge valve, or permanently by installing an __________ plate in the discharge.
Orifice
If it is a packing gland used if a pump, set the packing so that there will be leakage of approximately ___ drop per ____________.
1
Second
When making a lift station visit, for safety, how many operators should make the visit?
2
The __________ of the operating agency is the most significant factor determining the frequency of lift station visits.
Attitude
Lift stations should be checked how frequently?
Daily
Monitoring and telemetry systems are frequently referred to as SCADA which stands for?
Supervisory Control And Data Acquisition system
Wherever flows from one sewer meet and join the flow of another, the flow should always be going __________ in the same direction.
Downstream
High velocity cleaners, balls, kites, bags, parachutes, tires and scooters are all apart of what cleaning method?
Hydraulic cleaning
Bucket machines, power rodders, hand rods, and winches for pulling a variety of scraping equipment is apart of what cleaning method?
Mechanical cleaning
The cleansing action of high velocities of water in the line is considered?
Hydraulic cleaning
When cleaning sewer pipes at least __ operators are needed for cleaning lines up to 18 inches.
3
Do not attach a line to one nipple on the sewer cleaning ball, and then another line on the other nipple on the other side because this will reduce the __________ action desired for cleaning.
Swirling
A sewer cleaning ball method will function very well with ____ feet of head in the upstream manhole to create a ____________ velocity around the ball.
2.0
Scouring
When capturing debris from a balling sewer cleaning method, do not use a sand trap or retard the flow because it can hinder the _____________ of the balling operation.
Effectiveness