Wall Anchorage & Hardware Flashcards

1
Q

What is required on all anchor penetrations drilled into the slab system?

Who is responsible for scheduling it?

A

3rd party inspection

The framer schedules it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does the framer provide to the concrete tradepartner regarding wall anchors?

A

The framing tradepartner provides a plate-break layout to the concrete tradepartner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the only type of metal connection hardware used by Shea?

A

Simpson® brand hardware

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

On Simpson® hardware, what should be done with all the pre-punched nail holes?

A

They should all be filled with the appropriate nail

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

On Simpson® hardware can you nail through the hardware outside of a pre-punched nail hole?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the alternate for an MASA?

A

A Titen®

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How far from a plate break must a MASA be installed?

A

12”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

MASA anchors are nailed plumb within ______ of an inch?

A

1/2”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What’s the maximum gap allowed between the wood framing and a MASA or STHD?

A

1/8”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Titens® on an exterior plate are to be installed a maximum of ________ feet OC?

A

6’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Titens® on an exterior plate are to be installed within _______ inches from a plate break?

A

4” - 12”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

STHDs are nailed plumb within ______?

A

1 1/2”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Interior holddowns are ______ and ______?

A

HTTs and LTTs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you know how the interior bearing and shear walls are to be anchored?

A

Per the plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Interior non-bearing walls are anchored every ________ inches OC.

A

24”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

On interior non-bearing walls there should be _______ cut nails at each side of a door opening and at all plate ends.

A

2

17
Q

Keep all anchors a minimum of ________ inches away from the edge of the concrete slab.

A

1 1/2”

18
Q

Anchor embedment into concrete slabs is _______ inches, plus or minus _______ of an inch. (This does not apply to interior hold-downs).

A

2 1/4”

1/4”

19
Q

How do you secure a bottom plate that is less than 12” in length?

A

Adhesive, and a minimum of 2 cut nails or screws (if possible).

20
Q

How do you install cut nails, or pins when securing a bottom plate?

Why?

A

Staggered

To avoid splitting the plate

21
Q

Shear transfer connectors at eave blocks (A35/LS70) are to have a max gap of ________ of an inch between the connector and the wood.

A

1/8”

22
Q

Straps at the top of plate breaks and joints are to be installed _____________________________, not alongside the plate.

A

Over the top of the top plate

23
Q

STHD hold-downs are to be nailed to ______ full length king studs when possible. Nailing into one ______ stud and one ______ is acceptable.

A

2

One king and, one trimmer