Vocabulary Flashcards

1
Q

Activity

A

A task or process to be accomplished in a set period of time as part of working toward a larger project goal. An Activity can be assigned to a resource(s) and have an associated cost. Activities are ordered with logic links.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Actual Cost

A

The real amount paid or incurred for labor or materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Activity Relationship

A
An ordered link between 2 activities representing the order of execution.
The 4 relationship types are:
FS – Finish to Start
SS – Start to Start
FF – Finish to Finish
SF – Start to Finish
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Approved Change Requests

A

Documents of approved changes made to the project contract as a whole (cost, schedule, plan). These are first reviewed by all stakeholders before being approved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Arrow Diagraming Method (ADM)

A

Arrow diagramming method is a network diagramming technique used in Project Management in which activities are represented by arrows. ADM is also known as the activity-on-arrow (AOA) method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Backward Pass (Backward Plan)

A

Critical path calculation process which having calculated earliest date for activities on the network. Works backwards to find activities latest start and finish dates/float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Bar Chart

A

A chart on which activities are represented by Bars. The Bars length is represented by the activity Duration, and is lined-up on an X-axis time scale.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Base Line

A

A set of dates and costs frozen at the start of the project and used as a basis for performance evaluation as the project progresses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Budgeted Cost

A

The amount planned ahead and placed aside to execute an activity or an entire project from start to finish.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Change Estimate

A

An Estimate evaluating a potential change to a project. Often the estimate focuses on Cost, Schedule and Resource changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Change Impact

A

The effect of a project change on project cost, schedule and resourcing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Committed Cost

A

A cost which has not yet been paid, but an agreement, such as a purchase order or contract, has been made such that the cost is no longer recoverable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Cost Breakdown Structure (CBS)

A

A breakdown of the project into cost elements for cost control planning. A CBS will deconstruct a project into various cost elements or types such as area, phase, discipline, or materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Critical Activity

A

An activity that is on the project’s critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Critical Path

A

A project’s critical path is the sequence of network activities which add up to the longest overall duration. This determines the shortest time possible to complete the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Critical Path Method (CPM) Scheduling

A

: A project modeling technique and algorithm for scheduling a set of project activities. Developed in the late 1950s, CPM scheduling aims to build a model of a project that contains:

  1. A list of all activities required to complete the project (typically categorized within a work breakdown structure),
  2. The time (duration) that each activity will take to complete,
  3. The dependencies between the activities and,
  4. Logical end points such as milestones or deliverable items.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Critical Path Method

A

Scheduling then uses an algorithm that computes Early and Late dates for each activity in order to determine the project’s Critical Path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Critical Path Analysis

A

The analysis of a project schedule by its critical path or longest path. The analysis aims to understand whether the project can be completed on time and what key activities or milestones are a risk to the project’s timely completion. An advanced analysis may consider near-critical paths or other risk paths of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Date Constraint

A

A date restriction imposed on an activity’s start or finish date in scheduling software. Applying a constraint will swap the computed date to a date imposed by the user. Often used to imposed deadlines or to delay activities in a schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Direct Labor

A

1) Labor which can be directly related/allocated to the output of a productive account or cost center, compared with indirect labor which is not directly related to output. (2) Labor employed directly by owner or main contractor, as opposed to sub-contract labor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Doubled resource estimated duration (DRED)

A

Measures the length of an activity duration if the assigned level of resources has doubled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Duration

A

The number of calendar periods it takes (or is estimated to take) from the time the execution of an element starts to the moment it is completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Early Start

A

The earliest time an activity can start within the logic and imposed targets in the network.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Early Finish

A

The earliest time an activity can finish within the logic and imposed targets in the network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Estimate

A

Evaluation of expected quantities, time and man-hours, with allowances and provisions for expected unknowns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Estimated Cost

A

An approximated cost derived through a cost estimation technique such as using historicals or empirical methods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Estimate to Complete

A

The estimate of remaining costs, man-hours or quantities to the completion of defined scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Extensions of Time

A

A contractual extension of time to reflect agreed claims or scope changes. Sometimes used to minimize the risk of invoking penalty clauses.

29
Q

Float

A

Float is the amount of time that an activity in a project network can be delayed without causing a delay to: subsequent tasks (free float) or the project completion date (total float).

30
Q

Gantt Chart

A

A time-based activity chart in which a series of horizontal lines shows the amount of work done or production completed in certain periods of time in relation to the amount planned for those periods.

31
Q

Hammock

A

An activity, joining the start of the leading activity to the end of a series of network activities and where duration reflects the overall time and related logic for the series, at plan and subsequent monitoring stages.

32
Q

Histogram

A

Bar chart indicating estimated or actual manpower resources work or costs expended over time.

33
Q

Incurred Cost

A

Expenses incurred from project activities

34
Q

Indirects

A

Indirect costs are costs that are not directly accountable to an activity or work package. Indirect costs may be either fixed or variable. Indirect costs include administration and personnel. These are those costs which are not directly related to production. Some indirect costs may be overhead. But some overhead costs can be directly attributed to a project and are direct costs.

35
Q

KPI

A

A Key Performance Indicator is a type of performance measurement. KPIs evaluate the success of an organization or of a particular activity in which it engages.

36
Q

Lag

A

A scheduled delay on a logic link whereby a successor activity will be delayed with respect to a predecessor activity

37
Q

Late Finish

A

The latest possible date the activity must finish without affecting the target finish date for the project.

38
Q

Late Start

A

The latest possible start date for an activity to start without affecting the target finish date for the project.

39
Q

Lead

A

The amount of time whereby a successor activity can be advanced with respect to a predecessor activity. Often this is referred to a negative lag.

40
Q

Level of Effort Activity

A

A support-type project activity that must be done to support other work activities or the entire project effort.

41
Q

Loop

A

A logic error where a succeeding activity attempts to start prior to a preceding activity.

42
Q

Lost Time

A

Productive time lost because of inclement weather, labor problems, equipment failure or other cause

43
Q

Master Schedule

A

A high-level summary schedule or a schedule that is a combination of other independent sub-schedules.

44
Q

Milestone

A

An event to mark specific points in time along a project timeline. These points may signal anchors such as a project start and end date, a need for external review or input and budget checks, among others. In many instances, milestones do not impact project duration. Instead, they focus on major progress points that must be reached to achieve success.

45
Q

Monte Carlo Simulation

A

A computerized probabilistic method used in modeling risk.

46
Q

Network (Project Network)

A

A project network is a graph (flow chart) depicting the sequence in which a project’s terminal elements are to be completed by showing terminal elements and their dependencies. It is always drawn from left to right to reflect project chronology.

47
Q

Open ends

A

Any project Activities without a predecessor or a successor activity.

48
Q

Percent Complete

A

A percentage value between 0 and 100 that indicates the partial completeness of an activity, project or work package.

49
Q

PERT

A

Program Evaluation and Review Technique is a statistical tool, used in project management, which was designed to analyze and represent the tasks involved in completing a given project. First developed by the United States Navy in the 1950s, it is commonly used in conjunction with the critical path method (CPM).

50
Q

Physical Completion

A

Progress assessed by a physical measurement.

51
Q

Planning

A

Project planning is part of project management, which relates to the use of schedules such as Gantt charts to plan and subsequently report progress within the project environment. Initially, the project scope is defined and the appropriate methods for completing the project are determined.

52
Q

Planned Cost

A

An approved estimated cost for the project or items that will be used.

53
Q

Planning Engineer

A

A specialist engineer who develops the project timescale schedules, and manages them using a software package.

54
Q

Predecessor(s)

A

A predecessor activity is an activity that determines the start date or finish date of a following activity based on a logical relationship.

55
Q

Potential Change Requests

A

Documentation that tracks potential changes to your project’s estimated costs, resources or supplies. Allows you to identify any anticipated impacts to the project scope. Once reviewed by stakeholders, a change order can be requested to have these changes implemented.

56
Q

Precedence Diagramming Method (PDM)

A

Precedence Diagramming Method is a network diagramming technique used to establish order or execution in project schedules. PDM network diagrams use boxes, referred to as nodes, to represent activities and connects them with arrows that represent the dependencies between activities.

57
Q

Procurement

A

Procurement is the acquisition of goods, services or works from an outside external source. It is favorable that the goods, services or works are appropriate and that they are procured at the best possible cost to meet the needs of the acquirer in terms of quality and quantity, time, and location.

58
Q

Project Control

A

The setting and monitoring of cost/schedule deliverables, identification and anticipation of variances and implementation of preventive and recovery actions of approved changes.

59
Q

Resource Leveling

A

A process using resource analysis that aims to remove or reduce resource over-allocations

60
Q

Schedule

A

A schedule is a listing of a project’s milestones, activities, and deliverables, usually ordered with intended start and finish dates. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.

61
Q

Schedule Contingency

A

Extra duration that is added to the project’s schedule baseline during the planning phase to reduce any impacts of unforeseen events.

62
Q

Schedule Risk

A

Risk events that jeopardize completing the project on time

63
Q

S-Curve

A

Cumulative graph against time for tracking overall progress cf with plan: for cost, manhours, materials. etc. CP1/SP1 can be calculated from the variance on this form of graph.

64
Q

Target Date

A

A fixed activity due date or deadline

65
Q

The Work Breakdown Structure (WBS)

A

WBS is a hierarchical and incremental decomposition of the project into phases, deliverables and work packages. It is a tree structure, which shows a subdivision of effort required to achieve an objective; for example, a program, project, and contract

66
Q

Total Float

A

Total float is the difference between the finish date of the last activity on the critical path and the project completion date.

67
Q

Weighted Percent Complete

A

Overall progress completion measurement, using activity weightings to normalize disparate activities.

68
Q

Work Breakdown Structure

A

A work-breakdown structure (WBS) in project management and project controls, is a deliverable-oriented breakdown of a project into smaller components. A work breakdown structure is a key project deliverable that organizes the project’s work into manageable sections. See construction WBS examples here.

69
Q

Work Package

A

A work package (WP) is a subset of a project that can be assigned to a specific part for execution. Because of the similarity, work packages are often misidentified as projects.