Variance analysis equations Flashcards

1
Q

Overall materials variance

A

(standard quantity x standard price) - (actual quantity x actual price)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Materials price sub-variance

A

actual quantity x (standard price per unit - actual price per unit)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Materials usage sub-variance

A

standard price x (standard quantity - actual quantity)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Overall labour variance

A

(standard hours x standard rate) - (actual hours x actual rate)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Labour rate sub-variance

A

actual labour hours x (standard hourly rate - actual hourly rate)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Labour efficiency sub-variance

A

standard rate x (standard hours - actual hours)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Overall sales variance

A

(standard quantity x standard price) - (actual quantity x actual price)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Sales price sub-variance

A

actual quantity x (standard selling price - actual selling price)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Sales volume sub-variance

A

standard price x (standard quantity - actual quantity)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly