Value-Driven Delivery Flashcards
Present Value
Future Value/ (1 + i)^n
i = interest rate
n = number of years
450000/(1.06)^3
for 6% interest rate
Future Value
Known Value * (1 + i)^n
Known Value - what will it take to complete the project
i = interest rate
n = number of years
Net Present Value
Present value of a revenue stream over a period of time
Sum of cash flows / (1 + i)^n
Internal Rate of Return (IRR)
NPV of the project >= NPV of the benefits of the project
Cost Varience
Earned Value - Actual Cost
Earned Value
Earned Value is the amount of the task that is actually completed.
%Completed * Project total budget
Schedule Varience
Earned Value - Planned Value
Cost Performance Index (CPI)
Earned Value/ Actual Value
EV / AV
Schedule Performance Index (SPI)
Earned Value/ Planned Value
EV / PV
Estimate AT completion (EAC)
Budget at completion/ Cost Performance Index
EAC = BAC/ CPI
Estimate TO completion
Estimate at completion - Actual cost
To-Complete Performance Index
Effeciency needed to meet Budget At Completion (BAC)
(BAC - EV) / (BAC - AC)
Effeciency needed to meet Estimate AT completion (EAC)
(BAC - EV) / (EAC - AC)
> 1 - Hard to accomplish
= 1 - Same level of effeciency
<1 - Easy to accomplish
EVM Rules
Compute Earned Value
Variance means subtract
-ve means bad variance
Index means division
< 1 bad index
Key Performance Indicators (KPI) of Agile
Rate of Progress
Remaining Work
Likely completion date
Likely cost remaining
In Agile its all about getting this done
MoSCoW
Must Have
Should Have
Could Have
Will not have at this time