Value-Driven Delivery Flashcards

1
Q

Present Value

A

Future Value/ (1 + i)^n
i = interest rate
n = number of years

450000/(1.06)^3
for 6% interest rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Future Value

A

Known Value * (1 + i)^n

Known Value - what will it take to complete the project
i = interest rate
n = number of years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Net Present Value

A

Present value of a revenue stream over a period of time

Sum of cash flows / (1 + i)^n

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Internal Rate of Return (IRR)

A

NPV of the project >= NPV of the benefits of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Varience

A

Earned Value - Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Earned Value

A

Earned Value is the amount of the task that is actually completed.

%Completed * Project total budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule Varience

A

Earned Value - Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Performance Index (CPI)

A

Earned Value/ Actual Value

EV / AV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule Performance Index (SPI)

A

Earned Value/ Planned Value

EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate AT completion (EAC)

A

Budget at completion/ Cost Performance Index

EAC = BAC/ CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate TO completion

A

Estimate at completion - Actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To-Complete Performance Index

A

Effeciency needed to meet Budget At Completion (BAC)

(BAC - EV) / (BAC - AC)

Effeciency needed to meet Estimate AT completion (EAC)

(BAC - EV) / (EAC - AC)

> 1 - Hard to accomplish
= 1 - Same level of effeciency
<1 - Easy to accomplish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EVM Rules

A

Compute Earned Value

Variance means subtract
-ve means bad variance

Index means division
< 1 bad index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Key Performance Indicators (KPI) of Agile

A

Rate of Progress
Remaining Work
Likely completion date
Likely cost remaining

In Agile its all about getting this done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

MoSCoW

A

Must Have
Should Have
Could Have
Will not have at this time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

5 types customer preferences

A
Must-be quality
One-dimensional quality
Attractive quality
Indifferent quality
Reverse quality
17
Q

Requirements Priorotization Model

A

Value - Business Benefit

Cost - Expensive vs ROI

Risk - Riskiest items first

Difficulty of implementation - Safest first

Success factors - high probability of success

Regulatory compliance - laws and regulations

Relationship to other requirements

Stakeholder engagement

Urgency

18
Q

WIP

A

is risk

19
Q

WIP

A

hides bottlenecks

20
Q

WIP

A

requires investment

21
Q

WIP

A

delivers no return until complete

22
Q

WIP

A

needs to be limited

23
Q

Little’s Law

A

Duration of the queue is proportional to its size

24
Q

Lead Time

A

Amount of WIP / Avg., time to complete each work item

25
Q

Considerations for contracts in Agile

A

Scope changes
Priorities
Time and cost

26
Q

Dynamic Systems Development Method (DSDM) Strategy

A

Rapid Application Development benefits

  • Communication
  • Stakeholder Engagement
  • Transparency
27
Q

DSDM contracting

A

Creates Fixed Schedule, Cost and Quality

28
Q

Gulf of Evaluation

A

Difference between “whats said” vs “whats done”

29
Q

14 tasks in Value Driven Delivery

A

Plan work incrementally
Gain consensus on just in time acceptance criteria
Tune process to organization team and project
Release minimal viable product
Work in small batches
Review often
Prioritize work
Refactor code often
Optimize environmental operational in infrastructure factors
Review and checkpoint often
Balance value and risk
Reprioritize to maximize value
Prioritize non-functional requirements
Review and improve the overall process and product.