A practice guide for requirements elicitation offers the following information:
Disadvantages:
- Likely to be particularly time consuming to conduct.
- Difficult to separate fact from opinion.
Advantages:
- Provides an opportunity to build rapport.
- Provides an opportunity to explore various perspectives of the business
environment.
Which elicitation method is being referred to?
A - Interviews.
B - Workshops.
C - Focus Groups.
D- Observation.
A - Interviews.
Woody’s Bespoke Furniture has engaged a business analyst to define its requirements for automating currently paper-based business processes. The
documents that they wish to automate include the work requisition for craftsmen and the customer invoice.
Which of the following issues would the class model clarify?
A -Why a work requisition must be raised for a piece of furniture.
B - Who raises a customer invoice.
C- How many craftsmen can work on a piece of furniture.
D- When a customer invoice is sent to a customer.
C- How many craftsmen can work on a piece of furniture.
Topps Taxi service is in the process of moving its booking operations to a new online system. A meeting is taking place to prioritise the requirements for inclusion in the first release of the new application, which will take place in January and the second release is planned for April.
John is the owner of Topps Taxi and makes his requirements clear to the development team but later explains that having the ability to integrate airport
arrival information into his booking system would enable his drivers to receive alerts when flights are delayed or cancelled, saving wasted journeys - John considers this to be an essential part of the final solution. The development team indicate this
feature is similar to the traffic alerting service, which is in scope for the January release, and should, therefore, be fairly easy to develop.
With no proposed changes to timescales or budget, what priority will John’s extra requirement receive for the January release?
A- Must have.
B - Should have.
C- Could have.
D - Want to have, but won’t have this time.
C- Could have.
Patricia works for ABC Insurance Services, she has been asked to take on the role of sponsor for the project, which will look at the Claims Assessment System. She is new to the role of sponsor and has been researching her responsibilities.
Which one of the following suggested duties required of the project sponsor during requirements engineering is TRUE?
A - Ensure that the project is completed on time.
B - Assign the approval of the requirements to the project manager.
C- Allocate work to appropriate people working on the project.
D - Agree and sign off the project initiation document.
D - Agree and sign off the project initiation document.
A business analyst working on a project has just been notified of an update to a business policy, which will impact a set of baselined requirements. The business analyst will need to consult with the business stakeholders and agree on the change that needs to be made. They will also need to determine if any other related
requirements will be impacted.
Which elements of requirements management WOULD enable an effective response to this event?
Select all that apply.
A Requirements identification.
B Change control.
C Configuration management.
D Requirements cross-referencing.
B Change control.
D Requirements cross-referencing.
A charity has three business areas: fundraising, information technology and
finance. It has commissioned a project to introduce a new online charity donation ‘pick-up request’ service. The system will allow a person donating items (a user) to request a date for the collection of items they wish to donate. The donated items are then sold to raise funds for the charity.
The following requirements have been identified:
1) The user shall be able to enter items they wish to donate and request a
collection date.
2) The accounts system shall be able to support up to 20 concurrent users.
3) The solution shall be compatible with all commonly used browsers.
4) The user shall receive a text message confirmation of their collection date and donated items.
Which of the following represents the CORRECT categorisation of these
requirements by business area?
A 2x Functional (Fund Raising)., 1x Non-Functional (Finance)., 1x Technical (Information Technology).
B 1x Functional (Finance). 1x Non-Functional (Fund Raising). 2x Technical (Information Technology)
C 1x Functional (Fund Raising). 1x Non-Functional (Fund Raising). 1x General (Information Technology).
D 1x Technical (Finance). 2x Functional (Fund Raising). 2x Technical (Information Technology).
A 2x Functional (Fund Raising)., 1x Non-Functional (Finance)., 1x Technical (Information Technology).
A practice guide for requirements elicitation offers the following information:
Advantages:
Can provide a basis for developing prototypes.
Effective way of identifying exception conditions
Efficient method of revealing tacit knowledge.
Disadvantage:
Likely to be complex to develop.
To which elicitation method does this extract refer?
A Scenario analysis.
B Storytelling.
C Workshop.
D Interview.
A Scenario analysis.
A project sponsor is part of a review group, during the requirements validation stage of the requirements engineering framework.
The PRIMARY validation role of the project sponsor is to ensure that the
requirements are what at this stage?
A Technically feasible.
B Unambiguous.
C Aligned with business objectives.
D Compliant with quality standards and policies.
C Aligned with business objectives.
A business analyst is in the process of validating a set of requirements produced for a new business initiative. The following need to be agreed:
That the delivery of requirements is within budget.
That the requirements are technically feasible.
Who is responsible for agreeing these?
A Project manager, developers.
B Subject matter expert, developers.
C Project sponsor, testers.
D Project manager, testers.
A Project manager, developers.
A business analyst has just been informed by her project manager that a baselined requirement is likely to be removed or deferred from the set, to complete the project within a shorter timescale.
Which two elements of requirements management SHOULD be completed in
response to this event?
A Requirements cross-referencing.
B Change control.
C Software Support Tools.
D Requirements identification.
A Requirements cross-referencing.
B Change control.
The following requirements have been identified by a business analyst:
A. The system must allow users to record the date the order was dispatched
from the warehouse.
B. The system must allow the warehouse manager to view a summary of orders
placed by a customer.
C. The project must be managed in a way that is compliant with Health and
Safety regulations.
D. The interface of the system should be capable of a data transfer rate of
200Mbps.
In the requirements catalogue, which of these would be categorised as functional requirements?
A - B and C only.
B - A and B only.
C - C and D only.
D - A. B and D only.
B - A and B only.
William is a business analyst working on a project and through interactions with stakeholders, he has identified that some further elicitation could be helpful.
He has identified two areas to address:
1) Stakeholders need to be given more opportunity to discuss requirements.
2) Users need to be able to visualise the solution more clearly, to help them
communicate their requirements.
Which elicitation technique would BEST address both these issues?
A Scenario analysis.
B Focus group.
C Prototyping.
D Activity sampling.
C Prototyping.
A company is undertaking the requirements engineering for a new product. Some of the requirements are close to the limits of currently available technology. The Business Analyst has approached a senior developer to check the technical feasibility of the requirements.
In which stage of the requirements engineering framework SHOULD this action take place?
A Validation.
B Analysis.
C Documentation.
D Management.
B Analysis.
Hollybush Pet Food Company has initiated a project to introduce more efficient processes into its finance function, supported by a new IT system. It is now time to sign-off the requirements of the project and move into design and Philip, the Business Analyst, would like to hold a formal review of requirements. He has been asked to explain to the project sponsor why this is a good idea.
Which of the following reasons will he give for wanting to hold a formal review?
A. Allows requirements to be considered from different perspectives.
B. Removes the need for any other review of the requirements.
C. Allows defects in requirements to be identified before they are moved into
design.
D. Means that requirements do not have to be documented in detail.
A - A and D only.
B - B and C only.
C - A and C only.
D - C and D only.
C - A and C only.
A developer working to implement a set of baselined requirements has called the business analyst responsible for the project to check her understanding of a key requirement. During the conversation, it becomes clear to both parties that the developer is working on an older version of the requirement.
Which element of requirements management has failed?
A - Configuration management.
B - Change control.
C - Requirements identification.
D - Requirements cross-referencing.
A - Configuration management.