1
Q

What is another name for a mechanic’s or construction lien?

A

Statutory specific lien

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

T/F Lien rights apply to architects, engineers, and surveyors.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

T/F To sustain lien rights, a written lien notice must be given to the property owner.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What needs to be included in any written contract?

A

Written lien notice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If there was only a verbal agreement for work, what does the worker need to do?

A

Deliver the lien notice within 10 days of verbal agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How does a lien notice need to be delivered?

A

Personally or by certified mail

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How many days do subcontractors have to provide written lien notice?

A

Within 45 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly