Unit 4. Chapter 25. Project Management Flashcards

1
Q

Project

A

a specific and temporary activity with a starting and ending date, clear goals, defined responsibilities and a budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project management

A

using modern management techniques to carry out and complete a project from start to finish in order to achieve pre-set targets of quality, time and cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The key elements of project management

A
  • Defining the project carefully, including the setting of clear objectives
  • Dividing the project up into manageable tasks and activities
  • Controlling the project at every stage to check that time limits are being kept to
  • Giving each team member a clear role
  • Providing controls over quality issues and risks.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Consequences of failure to manage projects successfully

A
  • Penalty payments having to be paid to the customer
  • Bad publicity in the construction industry
  • Loss of future contracts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Reasons for project failure

A
  • Customers were not involved in the planning and development process.
  • The project had inadequate or no resources that were vital for its completion
  • Senior management just did not seem interested in seeing the project through
  • The project specification kept changing during the course of the project
  • Planning was poor
  • The project’s scope had become outdated due to change in business environment
  • The project team was technically incompetent.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Critical path analysis

A

a planning technique that identifies all tasks in a project, puts them in the correct sequence and allows for the identification of the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Process of using critical path

A
  1. Identify the objective of the project. E.g. learning biology A2 in 6 days
  2. Put the tasks that make up the project into the right sequence and draw a network diagram
  3. Add the duration of each of activities
  4. Identify the critical path - those activities that must finish on time for the project to be finished in the shortest time
  5. Use the network as a control tool when problems occur during the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Network diagram

A

the diagram used in critical path analysis that shows logical sequence of activities and the logical dependencies between them - and the critical path can be identified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Critical path

A

the sequence of activities that must be completed on time for the whole project to be completed by the agreed date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Network diagram notation

A
  • Arrow indicates each activity
  • An activity takes up time and resources
  • A node (circle) indicates the end of each activity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly