Unit 3 - Activity Planning and Risk Management Flashcards

1
Q

Objectives of Activity Planning:

A
  1. Feasible assessment
  2. Resource allocation
  3. Detailed costing
  4. Motivation
  5. Coordination
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is project scheduling?

A

Detailed planning of all the project activities. All the resources that are required for these activities should be efficiently delegated and each activity should have a start and an end date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the four phases of project scheduling?

A

Initial stage - which activities in what sequence

Second phase - activity risk analysis

Third phase - allocating resources

Last phase - creating project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are project activities?

A

Project activities are a set of tasks which on completion will result in achieving the goals of the project in complete the project itself

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Approaches to identifying activities

A

Activity based approach
Product based approach
Hybrid approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Steps to build a work breakdown structure (WBS)

A

Step one: find out desired project results

Step two: list the major tasks

Step three: defining smaller tasks from the major ones

Step four: continue the process. Find component tasks of smaller tasks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Explain the five levels of hybrid approach:

A

Level one: specify the project name example 1.0

Level two: deliverables. Example 1.1, 1.2, 1.3…

Level three: components. Denoted as 1.1.1, 1.1.2…

Level four: work packages

Level five: tasks, individual responsibilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are network planning models?

A

Project activities and their links are modelling network models

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Methods of network planning models

A

CPM and PERT (both use activity on arrow AOA)

Precedence diagram method uses activity on node AON

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Formulating network models

A
  1. Only one start node
  2. Only one end node
  3. Node has duration
  4. Links have no duration
  5. Precedents become immediate proceeding activities
  6. Time moves from left to right
  7. May not contain loops
  8. Cannot have dangles
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the risk?

A

Risk is an uncertain event that may or may not occur and can have a positive or negative impact on the project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the categories of risk?

A

Project risk
Technical risk
Business risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly