Unit-3 Flashcards

1
Q

Additional insured:

A

Parties other than the named insured that are protected by a policy endorsement giving them direct protection for claims arising under the policy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Adjudication:

A

In the BIM Addendum, a decision by a court of law or arbitration about whether an owner owes a payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Affiliated Contract:

A

A project contract with a consultant, subcontractor, supplier, or other third party (that is, other than a Governing Contract between the owner and architect/engineer or the owner and the contractor, CM, or design/builder) that requires the party to contribute to or use project modeling, and to which the BIM Addendum is attached or incorporated by reference.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The American Institute of Architects (AIA):

A

The leading professional membership association in the United States for licensed architects, emerging professionals, and allied partners since 1857, www.aia.org.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The American Institute of Steel Construction (AISC):

A

The leading professional membership association in the United States for design professionals, owners, and general contractors using steel construction. Founded in 1921, www.aisc.org.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Analysis software:

A

Applications developed for the purpose of conducting complete engineering or other analyses of 3D modeling (for example, RISA-3D, RAM, STAAD.Pro, and ETABS).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Architectural work:

A

The design of a building embodied by design records, including the building structure itself.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The Associated General Contractors of America (AGC):

A

The leading national construction trade association representing all facets of commercial construction for both public and private entities including building, heavy, highway, and municipal projects. AGC and its nationwide network of chapters are recognized as the leaders in defining and advocating for the construction industry for nearly a century, www.agc.org.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Author:

A

A party that creates intellectual property.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

BIM Project Execution Plan or BIM PXP:

A

A document (tool) jointly created by the owner, contractor, and architect/engineer representatives for the project that specifies the use of BIM, modeling conventions, model scheduling, and model exchanges between the parties using BIM on the project. The BIM Project Execution Plan is required to be created under the BIM Addendum and can be used as an independent document.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

BIM liability insurance:

A

A policy of insurance currently being developed that will provide greater coverage for an individual’s errors and omissions in making contributions to a model, rework needed to correct a model due to interoperability problems, and the need for recertification of a model due to negligence in contributing to or using a model.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Builder’s risk insurance:

A

This insurance covers risks associated with unexpected losses to the work during construction, such as weather-related damage, theft, flood, and collapse of a partially completed structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Building Information Modeling (BIM) Addendum:

A

Endorsed by a wide range of owner and construction industry groups, the BIM Addendum fosters the collaborative use of Building Information Modeling that appropriately balances critical interests and concerns of everyone who contributes to and uses BIM on a project. See ConsensusDocs, www.ConsensusDocs.org.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Claims-made:

A

Insurance that covers only claims that the insured becomes aware of, or should have become aware of, during the policy period, even if the act, error, or omission that gave rise to the claim occurred before the policy period began.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Co-authors:

A

One of two or more parties who contribute to a single work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Collaborative BIM:

A

A process where the project owner, architect/engineer, and contractor (and often, the subcontractors, supplier/manufacturers, tenants, and others) all participate in creating and using a model(s) for the project. This process is sometimes referred to as “big BIM.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Commercial General Liability Insurance (CGL):

A

Insurance coverage that protects the party it insures against risks of accidental physical injury to persons or property arising from negligence in performance of contracted work operations on a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Completed operations:

A

A project on which the construction operations are complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

ConsensusDocs™:

A

ConsensusDocs contracts are written and endorsed by a coalition effort of 40 leading construction associations. The coalition’s goal is to draft fair documents that incorporate best practices to improve the design and construction industry. The library includes more than 90 contract documents covering all methods of project delivery. ConsensusDocs was the first to publish standard documents comprehensively addressing IPD (300); BIM (301); and Green Building (310), www.ConsensusDocs.org.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Consequential damages:

A

In the context of the BIM Addendum, consequential damages include injury to anything other than the models themselves that arise as a consequence of model use or access.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Constraints:

A

Formatting that establishes how the software will interpret specific design elements, such as walls, windows, doors, stairs and other primary building objects, in the growing model.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Constructability review:

A

A process by which conflicts among various contributions of data and information to a model are resolved; sometimes referred to as clash detection, clash resolution or spatial coordination. Representatives of each Contributor work together to identify design conflicts and to reach an agreement on the best means of resolving them during this process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Construction Model:

A

A term created in the BIM Addendum for a Model that (a) consists of those aspects of the project that are to be modeled as specified in the BIM Execution Plan prepared pursuant to this Addendum; (b) utilizes data imported from Design Models or, if none, from a designer’s Construction Documents; and (c) contains the equivalent of shop drawings and other information useful for construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Contract Document:

A

A document that the parties agree contains binding contractual obligations between them, rather than being solely advisory or informational. In the ConsensusDocs family, the Agreement, drawings, specifications, addenda issued prior to execution of the Agreement, approved submittals, information furnished by the project owner, and other documents listed by the parties, including any modifications issued after execution, are typically Contract Documents. Models may, but are not automatically presumed to be, Contract Documents under the BIM Addendum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Contractor:

A

The party on the project responsible for performing and overseeing construction by the party’s own and/or hired forces.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Contractor Controlled Insurance Program (CCIP):

A

A type of specialty coverage intended to avoid gaps in coverage among the three main construction insurances. See also Owner Controlled Insurance Program and Wrap Up Insurance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Contractual privity:

A

Having a contractual relationship between two parties. A lack of privity may limit a party’s ability to assert claims. In the Design-Bid-Build construction context, a lack of contractual privity of the contractor with the architect/engineer results in the contractor being able to assert design defect claims to the owner, with whom the contractor is in privity. See also Spearin Doctrine.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Contribution:

A

The expression, design, data, or information that a party (a) creates or prepares, and (b) incorporates, distributes, transmits, communicates, or otherwise shares with other parties for use in or in connection with a model for a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Contributor:

A

A party who creates, prepares, incorporates, distributes, communicates, or otherwise shares a Model or Model data with others on a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Convention:

A

A technical practice or protocol that is followed to govern model content definition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Copyright:

A

Property rights granted to protect works of authorship, such as writings, music, and works of art that have been tangibly expressed, or reduced to a fixed form.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Copyright infringement:

A

Wrongful use of intellectual property or proprietary data derived from copyrighted work without permission from the copyright owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Construction Manager-at-Risk (CM at-Risk):

A

Project delivery method where the owner has a contract with the CM at-Risk and another directly with the designer. The constructor typically provides essential pre-construction services, holds the trade contracts, takes responsibility for the performance of the work and guarantees the construction costs and schedule. The CM-at-Risk also serves as the prime contractor, assuming the risk of the performance, either by its own crews or by specialty contractors and suppliers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Data repurposing:

A

When integrating model designs or data using different software programs and one software lacks the ability to correctly interpret data generated by the other software, and so ignores (does not depict) or changes the first software’s model data when viewed or read by the second software.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Deliverable:

A

A deliverable is the product of engineering or design efforts. Typically, this would include a concept submittal and the corrected final design. A deliverable may have multiple phases.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Derivative work:

A

A work that is taken, translated, adapted, or in some way further developed from a previous copyrighted work. This subsequent product, in its derived form, enjoys copyright protection only to the extent of material independently contributed by the author of this additional work. Derivative of a derivative: An adaptation of a derivative work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Design-Bid-Build:

A

A method of project delivery in which the owner procures a design and bid package from an independent architect/engineer, uses competitive bidding to get bid prices for all work required to build the project as specified, and then selects a constructor to build the project, often on the basis of the low bid received from a responsible constructor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Design-Build:

A

A method of project delivery in which one firm assumes responsibility for both the design and the construction of the project. By combining these two functions from the outset of the project, Design-Build can promote a more collaborative team approach throughout the entire duration of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Design-Build Insurance:

A

Furnishes coverage for negligently-caused errors in design and construction of a project delivered on a Design-Build basis. The intent of this insurance is to furnish the equivalent coverage traditionally offered through both CGL coverage and professional liability coverage without a gap of uncovered loss between the two.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Design Model:

A

Those aspects of the Project that (a) are to be modeled as specified in the BIM Execution Plan prepared pursuant to the BIM Addendum and (b) have reached the stage of completion that would customarily be expressed by the architect/engineer in 2D design documents ready for construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Derivative work:

A

A work that is taken, translated, adapted, or in some way further developed from a previous copyrighted work. This subsequent product, in its derived form, enjoys copyright protection only to the extent of material independently contributed by the author of this additional work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Derivative of a derivative:

A

An adaptation of a derivative work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Design-Bid-Build:

A

A method of project delivery in which the owner procures a design and bid package from an independent architect/engineer, uses competitive bidding to get bid prices for all work required to build the project as specified, and then selects a constructor to build the project, often on the basis of the low bid received from a responsible constructor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Design-Build:

A

A method of project delivery in which one firm assumes responsibility for both the design and the construction of the project. By combining these two functions from the outset of the project, Design-Build can promote a more collaborative team approach throughout the entire duration of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Design-Build Insurance:

A

Furnishes coverage for negligently-caused errors in design and construction of a project delivered on a Design-Build basis. The intent of this insurance is to furnish the equivalent coverage traditionally offered through both CGL coverage and professional liability coverage without a gap of uncovered loss between the two.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Design Model:

A

Those aspects of the Project that (a) are to be modeled as specified in the BIM Execution Plan prepared pursuant to the BIM Addendum and (b) have reached the stage of completion that would customarily be expressed by the architect/engineer in 2D design documents ready for construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Designer:

A

The design professional on the project responsible for performing and overseeing overall project design.

48
Q

Dimensional accuracy:

A

A specific determination of the level of detail in the Project Models and whether it is accurate enough to take scaled measurements directly from the Models.

49
Q

Drawings:

A

Any (a) two-dimensional plans, sketches, or other drawings that are created separately, and not derived, from a model and (b) two-dimensional projections derived from a model supplemented with independent graphics or annotations. In the BIM Addendum, this term means only such two-dimensional documents that are also specified by the parties as Contract Documents. See also Contract Document.

50
Q

Duty of ordinary care:

A

The care that a reasonably prudent party in the same profession and geographic area would exercise when confronted with similar facts and circumstances. See also ordinary care.

51
Q

Electronic Communications Protocol (ECP) Addendum:

A

An Addendum to a contract that establishes protocol for electronic communications to be strictly followed by all project contributors. See ConsensusDocs.

52
Q

Elements:

A

Individual design components within BIM software that allow designers to create three-dimensional designs quickly and easily.

53
Q

Errors and Omissions (E&O) Insurance:

A

Protects professional service providers from damages or losses due to acts of negligence, or non-intentional acts, errors, or omissions in performance of their professional activities on a project. See also Professional Liability Insurance.

54
Q

Excess Policy:

A

A supplemental policy that increases the total amount available to pay for the same kinds of losses covered by another policy. See also Umbrella Policy.

55
Q

Federated Model:

A

A Model that is composed of multiple Models representing the input from all design disciplines on a project. The Model evolves through an iterative process where each subsequent iteration represents an advancement of the project designs. Ultimately, the Federated Model incorporates all 3D geometry and related object information. Under the BIM Addendum, contributions to a Federated Model do not become merged or altered and can be separated out of the Federated Model.

56
Q

Flow down clause:

A

A contract provision that requires the contracting parties to include the same or comparable term in other contracts they enter into for the same project. For example, in the ConsensusDocs BIM Addendum §1.2, parties that enter into Governing Contracts are required to append or incorporate the Addendum into their Governing Contract, but that section also has a flow down clause requiring those same parties to attach the Addendum to any other project contract where those third parties will participate in modeling.

57
Q

Format:

A

An agreed upon process that all Contributors to a Model consistently follow in naming files, objects, schedules, and other design elements. This may also include specific file structures for saving and exchanging Model data or certain software to develop and keep Model data secure.

58
Q

Full Design Model:

A

A Model consisting of coordinated structural, architectural, MEP, and other Design Models designated in the BIM Execution Plan to be produced by the design team.

59
Q

Governing Contracts:

A

The principal agreements between the project owner and contractor (or construction manager or design/builder), and the project owner and the architect/engineer for a project. Granularity: The level of detail depicted to scale accurately in a model. See also dimensional accuracy.

60
Q

Hard clash:

A

When two components physically overlap in the same space depicted on a virtual 3D model.

61
Q

Indemnitee:

A

A party protected by another party under a contract provision that shifts liability such that the indemnitor agrees to answer for the harm suffered by the indemnitee.

62
Q

Indemnitor:

A

A party who has a duty to make good a loss, damage, or liability incurred by another party by means of a contract provision that shifts liability from one party to another.

63
Q

Indemnity:

A

A duty undertaken by one party to make good a loss, damage, or liability incurred by another party. A contract provision that shifts liability from one party to another.

64
Q

Industry Foundation Classes (IFCs):

A

IFCs are data elements that represent parts of buildings, or elements of the design process, and contain the relevant information about those parts. IFCs are used by computer applications to assemble a computer-readable model of the facility that contains all the information of the parts and their relationships to be shared among Project Participants. The BuildingSMART Alliance has created this non-proprietary data exchange format to mitigate interoperability problems in modeling. See also interoperability.

65
Q

Information Management:

A

The measures that protect and defend model information and information systems with respect to their availability, integrity, authentication, confidentiality, and non-repudiation.

66
Q

Information Manager (IM):

A

he party responsible under the BIM Addendum for coordinating the measures that protect and defend model information and information systems with respect to their availability, integrity, authentication, confidentiality, and non-repudiation.

67
Q

Information Technology (IT) Administrators:

A

Representatives for the project owner, contractor, and architect/engineer who are authorized and responsible to coordinate their respective party’s compliance with the technical protocols and procedures related to information technology use, including BIM, for the project under the ECP Addendum.

68
Q

Information Technology (IT) Management Coordinator:

A

Provides dayto-day technology management and coordination for all project electronic communications issues.

69
Q

Information Technology (IT) Management Team:

A

The owner IT Administrator, contractor IT Administrator, and architect/engineer IT Administrator form this group, which is given the responsibility to jointly develop procedures, protocols, and practices needed for the effective administration of electronic communications information, modeling, and documents determined to be necessary for the project. Injunction: Legal proceeding to stop wrongful use of intellectual property or proprietary data.

70
Q

Integrated Project Delivery (IPD):

A

Also known as Integrated Practice, a project delivery method that leverages intellectual and physical resources using the best available tools to produce the highest quality product by placing project owner, contractor, and architect/engineer at risk for profit or loss on the project. It requires ongoing shared team knowledge that is well facilitated through extensive BIM use.

71
Q

Intellectual property (IP):

A

A commercially valuable, intangible asset, such as a copyright, trademark, or patent.

72
Q

Intelligent:

A

An element or object in the model that is data-rich, or able to furnish additional information about itself, such as its length, width, size, model number, or other physical attributes.

73
Q

International Alliance for Interoperability (IAI):

A

Consists of software companies, building product manufacturers, information publishers, owners, designers, and builders in AEC and other industries whose goal is to develop a universal standard for model data information sharing. See also buildingSMART.

74
Q

Interoperability:

A

The exchange of information among project participants throughout the lifecycle of a facility by direct communication between software applications. This is accomplished via a common set of exchange formats to read and write data similarly and to use the same protocols.

75
Q

Liability:

A

Legal obligation or responsibility to do or to refrain from doing something. Common law can impose general liability. Contract terms, agreed upon between parties, create and/or limit general liability.

76
Q

License:

A

The authorization of a copyright owner to another for use of intellectual property or proprietary data while continuing to retain ownership of the work and data.

77
Q

Model:

A

A 3D representation of a building, aspect, or project in digital virtual form. Model Facilitator: A manager created under the ECP Addendum to facilitate BIM use on a project. The BIM Addendum’s Information Manager (IM) also may be appointed to fulfill the Model Facilitator role.

78
Q

The National Building Information Model Standard (NBIMS):

A

Committee of the National Institute for Building Sciences (NIBS) Facility Information Council (FIC) that created IFCs. Since 1992 the FIC mission has been to “improve the performance of facilities over their full lifecycle by fostering common and open standards and an integrated lifecycle information model for the AEC and FM industry.”

79
Q

The National Institute of Building Sciences (NIBS):

A

Authorized by the U.S. Congress in the Housing and Community Development Act of 1974, Public Law 93-383. In establishing NIBS, Congress recognized the need for an organization that could serve as an interface between government and the private sector to improve the building regulatory environment, facilitate the introduction of new and existing products and technology into the building process, and disseminate nationally recognized technical and regulatory information.

80
Q

nD model:

A

Beyond 5D. The integration of other aspects or analyses of the 3D model, such as safety, energy, indoor air quality, lighting, etc. See also xD model.

81
Q

Negligence:

A

The failure to exercise the standard of care that a reasonably prudent person would have exercised in a similar situation; any conduct that falls below the legal standard established to protect others against unreasonable risk of harm, except for conduct that intentionally, wantonly, or willfully disregards others’ rights.

82
Q

Non-collaborative BIM:

A

A model created independently by a party for its own purposes. Sometimes referred to as “silo BIM” or “little BIM.”

83
Q

Non-exclusive license:

A

A license granted by a copyright owner for use to one party while keeping the ability to grant others the same right.

84
Q

Object:

A

A physical entity or event depicted in a model (whether 2D or 3D) that may or may not possess any related properties. An object can be a single designelement, or composed of many elements and components that would be more burdensome if treated as separate parts of the Project Model.

85
Q

Object enabler:

A

An application written by a software developer that allows its custom, or proprietary, objects or elements to be viewed in a different software application environment. Object enablers may be available at no charge from the website of a modeling software application developer.

86
Q

Object families:

A

Libraries of cut-and-paste templates for common design elements included in most BIM software. These libraries include common design features, such as walls, roofs, windows, doors and trim, stairs, railings, ramps, cabinets, landscaping, and light fixtures.

87
Q

Occurrence basis:

A

A policy of insurance that provides that if the insured harms persons or property and causes a loss that occurs during the policy coverage period, the insurance carrier issuing that policy will pay for that loss (up to the dollar amount of coverage limits), even if the claim is first made after the end of the policy period.

88
Q

Open interoperability standards:

A

Non-proprietary protocols and data structures that support the exchange or joint use of digital information by differing software tools.

89
Q

Ordinary care:

A

Care that a reasonably prudent party in the same trade and geographic area would exercise when confronted with similar facts and circumstances. See also duty of ordinary care.

90
Q

Owner Controlled Insurance Program (OCIP):

A

A type of specialty coverage intended to avoid gaps in coverage among the three main construction insurances. See also Contractor Controlled Insurance Program and Wrap Up Insurance.

91
Q

Parametric:

A

Software objects/elements that reflect or describe the real-world behaviors and attributes of construction materials, equipment, and assemblies depicted. Objects possess characteristics of construction materials, equipment, and assemblies and also depict the interrelationship and interaction among them. Consistent relationships are maintained among elements as the model is manipulated.

92
Q

Patent:

A

Property rights granted for original inventions to limit others from making, using, or selling the invention.

93
Q

Payment bond:

A

A bond wherein a surety ensures that the general contractor will pay its bills to subcontractors and suppliers.

94
Q

Performance bond:

A

A bond wherein a surety guarantees to the owner that it will provide financial assurance that the contractor will perform its contract obligations.

95
Q

Phase:

A

A portion of work that arises from sequencing work in accordance with predetermined stages.

96
Q

Policy limits:

A

The contracted maximum amount an insurer is obligated to pay on an insured’s behalf pursuant to the policy of insurance.

97
Q

Professional Liability Insurance:

A

Protects professional service providers from damages or losses due to acts of negligence, or non-intentional acts, errors, or omissions in performance of their professional activities on a project. See also Errors and Omissions (E&O) Insurance.

98
Q

Professional services:

A

Services provided by a licensed professional, such as an architect, engineer, or construction manager.

99
Q

Project Model:

A

Model consisting of the federation of a Full Design Model and one or more Construction Models designated in the BIM Execution Plan to be produced by the parties contributing to the Models.

100
Q

Project Participants:

A

All of the parties that have Governing Contracts and Affiliated Contracts, who will contribute to the Model and/or will use it to analyze, construct, or operate the buildings depicted in the completed Models.

101
Q

Quantity takeoff:

A

The ability to count, measure, and extract any or all of the identified elements contained in a 3D model.

102
Q

Scheduling:

A

A sequence of activities based upon the elements of a construction plan and reflecting the decisions made with all the project’s known objectives and constraints in mind. It is output generated from the construction plan or 3D model.

103
Q

Shop drawings:

A

Drawings prepared by licensed design professionals that illustrate means and methods of implementing work consistent with an architect’s designs.

104
Q

Soft clash:

A

Two or more model elements that violate space constraints imposed by code or design limitations without physical overlap. These typically include clearance around objects, tolerances needed for safe operation, and egress requirements.

105
Q

Spatial coordination:

A

For design coordination and constructability, to check work digitally before putting it in place in the field. (Synonyms: interference, collision, conflict, clash detection, variance, coordination.)

106
Q

Spearin Doctrine:

A

A legal concept based on a decision issued in 1918 by the United States Supreme Court in United States v. Spearin, 248 U.S. 132, 39 S. Ct. 59, 63 L. Ed. 166. It held that a contractor has a right to expect that plans and specifications the contractor uses for construction under a Design-Bid-Build project delivery method are adequate. Specifically, the court held that “if [a] contractor is bound to build according to plans and specifications prepared [for] the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications.”

107
Q

Tail Coverage:

A

A rider to a CGL policy of insurance that extends the coverage period. Tail coverage usually covers claims made in multiple-year increments after completion of the project, or after expiration of the original policy.

108
Q

Trademark:

A

Intellectual property rights that protect words, names, symbols, sounds, or colors that distinguish goods and services from those manufactured or sold by others and indicate the source of goods. Project marketing symbols are commonly trademarked to distinguish a unique project from those offered by competing developers.

109
Q

Umbrella Policy:

A

A supplemental policy that increases the total amount available to pay for the same kinds of losses covered by another policy. See also Excess Policy.

110
Q

Value engineering:

A

A process undertaken during the design phase in which elements or components of the design are evaluated for ease of constructability, and to incorporate design features that provide comparable performance at better cost or schedule savings.

111
Q

Virtual Design and Construction (VDC):

A

The use of integrated multi-disciplinary performance models of design-construction projects, including the product (i.e., facilities), work processes and organization of the design-construction-operation team in order to support explicit and public business objectives. “VDC models are virtual because they show computer-based descriptions of the project.” (Kunz & Fischer 2007)

112
Q

Waiver:

A

A relinquishing, or giving up, of a right possessed by a party.

113
Q

Webmaster:

A

The person or party that provides day-to-day operation and maintenance of a project website.

114
Q

Work for hire:

A

A work created by an author, employed by another under a work relationship or a written agreement, who conveys the copyright ownership for the work to the employer either before or after completion of the work.

115
Q

Wrap Up Insurance:

A

A type of specialty coverage intended to avoid gaps in coverage among the three main construction insurances. See also OwnerControlled Insurance Program and Contractor-Controlled Insurance Program.

116
Q

xD model:

A

Beyond 5D. The integration of other aspects or analyses of the 3D model, such as safety, energy, indoor air quality, lighting, etc. See also nD model.