Tri 2 Exam Revision Flashcards
What are the key contract admin activities?
- Ensuring compliance
- Subcontract letting & administration
- Managing variations, progress claims & disputes, accounting, invoicing and payment, ext. of time
- Cost control
Risk: Contract Price
Lump Sum or Rate contract
Risk: Quantities
Whether principal provides estimates of quantity
Risk: Latent Site
Eg; Soil Conditions
Risk: Site Possession
Giving access to a contractor on time
Risk: Practical Completion
Balance between benefit & cost of contract period
Risk: Delay
Risk of blowout vs Tender Price
Risk: Variation
Agreement on prices prior to changes
Risk: Security
Risk of Liability vs Tender price
Warranties
- An assurance that specific facts or conditions are true or will happen
- May be expressly set out in the contract
- A breech of warranty gives right to claim damages
Guarantees
- An undertaking that one party (guarantor) gives to a second party (beneficiary) to be responsible for the debts or defaults of a third party (guaranteed party) in respect of a transaction between the second and third parties (guaranteed obligations)
- A guarantee provides the beneficiary with security for the performance by the guaranteed party of the guaranteed obligations.
Security
- A party provides security under a contract as a financial pledge that it will perform its obligations under that contract.
- If the party defaults, it loses the amount pledged
- The contractor and the principal must provide security: time for provision if nothing stated, within 28 days after acceptance of tender
- Failure to do this within the time specified will result in a substantial breech of contract (cl.44)
Security - Bonds or Guarantees
A contract guarantee (security) in the form of cash, bonds or inscribed stock, interest bearing deposit etc is usually required to be given by the contractor in accordance with the terms of the contract for the purpose of ensuring the due andproper performance of the contract
Security - Retention
- Retention is a percentage of the amount certified as due to the contractor on an interim certificate, that is deducted from the amount due and retained by the client.
- The purpose of this is to ensure that the contractor properly completes the activities required of them under the contract
- Usually between 2.5%-10% of each progress payment
Builders Obligations
CL 10.1
Warranties
-Carry out works in proper an workmanlike and in accordance with plans and specifications
-Materials are good and suitable for purposes
-Carry out works in accordance with laws
-Will achieve completion by specified date
CL10.3 - 10.4
Payment Claims
-Builder will give to owner written progress claim
-Builder will gives to owner written financial claim