Transformers: Chapter 6 - Possible Test Questions - WEEK 13 Flashcards

1
Q

WYE - WYE BANK:

A
  • With a Wye - Wye bank, each transformer is connected to the system between a phase and grounded neutral.
  • In addition, each of the three transformers provide one hot leg on the secondary side to deliver three- phase power. For this reason, three-phase power can only be supplied with three transformers.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

An open bank would not provide three-phase power if the secondary were connected:

A
  • Open WYE
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

WYE - WYE BANK (SECONDARY)

A
  • The secondary coils are paralleled, leaving the x3 lug idle. It is strongly recommended that paralleling be done between the xl and x2 rather than the x1 and x3. The x2 bushing is considered the neutral position and should be treated as such.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Wye connected banks have two main advantages:

A
    1. All three transformers can share the single-phase load equally.
    1. They can be built using single or dual primary bushing transformers.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The disadvantage for a WYE-WYE Bank:

A
  • is that if one transformer fails, the customer is down to one phase until the defective transformer is fixed or replaced.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

WYE - DELTA BANK:

A
  • With a Wye - Delta bank, each transformer is connected to the system and the Wye point is floated (not grounded). Because the Wye point is floated, transformers with two primary bushings must be used.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

WYE - DELTA BANK

- With one unit out of service, a bank of single-phase units can be reconnected as an:

A
  • open Wye - open Delta, which may temporarily supply power to the customer until permanent repairs are made.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

WYE - DELTA BANK

- Grounding the Wye point would create a:

A
  • ground source for the primary system. This could subject the transformer to severe overloading during a primary system disturbance or load imbalance. Because the Wye point is floated, this connection can be used on both three- and four-wire systems.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

WYE - DELTA BANK

- With one unit out of service, a bank of single-phase units can:

A
  • be reconnected as an open Wye - open Delta, which may temporarily supply power to the customer until permanent repairs are made.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

WYE - DELTA BANK

- How are he secondary coils are connected:

A
  • in series.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

WYE - DELTA BANK

- The voltage between the neutral and the power leg (designated as ‘p’ above) is:

A
  • 1.73 times greater than the neutral to hot leg voltage.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

WYE - DELTA BANK

- The power leg has no use electrically and is simply a by-product of a:

A
  • Delta secondary. Three-phase motors only see the h - h voltage and do not “notice” the power leg. It is very important to avoid confusing the power leg with hot legs when connecting to 120-volt lighting loads.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

WYE - DELTA BANK

- The floating Wye point can be a:

A
  • hazard to lineworkers because it is not grounded.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

WYE - DELTA BANK

A power leg only exists on:

A

Delta and open Delta secondaries when a ground is attached to the winding midpoint of one of the transformers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

WYE - DELTA BANK

Delta secondaries do not allow all three transformers to:

A

share the single- phase load equally; therefore, one transformer of the bank must provide the majority of the lighting load. It will always be the transformer with the x2 grounded serving as a neutral. Because this transformer must provide the majority of the single-phase load, it must be sized larger than the other two transformers in the bank, and is referred to as the lighter transformer because it handles the “lighting” load. The other transformers share somewhat equal portions of single-phase and three-phase load and are referred to as power transformers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

DELTA - WYE BANKS

-

A
  • With a Delta - Wye bank, the H2s are connected to the H1s, creating a symmetrical pattern, and then connected to each phase of the system. The primary Delta connection is suitable for both three- and four-wire systems.
17
Q

DELTA - WYE BANKS

- The secondary Wye connection of a Delta - Wye is the same as:

A

with the Wye - Wye bank and as shown previously.

18
Q

DELTA - DELTA BANKS

-

A

With a Delta - Delta bank, the primary connection is suitable for either a three- or four-wire system. With one unit out of service, a bank of single-phase units can be reconnected as an open Delta, open Delta bank. With one of three identical units out of service, the rating of the bank when supplying only three-phase load is about 57.7% of the bank rating when all three units are in service.

19
Q

DELTA - DELTA BANKS

- As mentioned before, Delta secondaries do not allow:

A

all three transformers to share the single-phase load equally; therefore, one transformer of the bank must provide the lighting load. It will always be the transformer with the x2 grounded serving as a neutral. Because this transformer must provide the majority of the single-phase load, it must be sized larger than the other two transformers in the bank and is referred to as the lighter transformer.

20
Q

When supplying three-phase power from underground systems, the transformers used are:

A
  • three-phase transformers. The coils are banked internally and the leads are brought up to the primary and secondary bushings.
21
Q

When pad-mounted or subsurface transformers are used,:

A
  • the system voltage and the service voltage needed can be found on the nameplate of the unit.
22
Q

THREE-PHASE UNDERGROUND TRANSFORMERS

- The lineworker must rely entirely on

A

the nameplate to determine which primary and secondary connections were made at the factory.

23
Q

Although banking transformers in an underground system is rare, some utilities install

A

open Wye - open Delta banks using two single-phasepad-mounted transformers. The banking is performed with the secondary cables through short ducts.

24
Q

NON-STANDARD CONNECTIONS

- Three-Phase 120/208 from V-Phase Primary

A

A three-phase 120/208-volt service can be supplied even if only two phases of a Wye primary (V-phase) are available. One transformer in the bank should not be less than twice the size of either one of the other two transformers, and its secondary coils must be connected in series.

25
Q

NON-STANDARD CONNECTIONS

- 120/240 Single-Phase and 120/208 Three-Phase:

A

The primary connection can be either Wye or Delta depending upon the system voltage and the primary coil voltage ratings. One transformer in the bank should not be less than twice the size of either one of the other two transformers, and its secondary coils must be connected in series.

26
Q

NON-STANDARD CONNECTIONS

-Corner Ground:

A

Some customers need only three-phase three-wire services. Examples of this may be a customer with an irrigation pump remotely located. There may be no need for lights at the pump location. However, the NESC still requires a ground reference between the pump and the transformer bank. To satisfy this requirement without installing a neutral conductor, some utilities install corner grounded banks with the most common being the Delta corner ground.

27
Q

NON-STANDARD CONNECTION:

- Corner Ground II:

A

Nearly every lineworker who is first exposed to this connection is surprised that it can work. The best explanation is that a Delta or Wye can be grounded one time at any coil terminal and still operate properly. Grounded Wye connections are grounded one time at the H2 or x2 terminals. Delta secondaries are normally grounded at the midpoint terminal of one transformer. With a corner ground, the ground is installed on one of the corners.