TPP Flashcards

1
Q

State the purpose of a Training Project Plan (TPP).

A

This is the blueprint CCMM uses to devolop or revise curriculum. It desribes the factors and elements required to perform operations and procedures to conduct a successful training programd procedure It includes POA&M, personnel, hardware, and funds required to achieve a successful program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who has initial approval authority of a TPP?

A

CCA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

who approves implementation of a TPP ?

a. Submitted to NETC per triggered event with zero sum gain.
b. Submitted to NETC requiring additional resources or offsets.

A

a. NETC N7 approves implementation of TPP w/o offsets

b. OPNAV approval requiring offstes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Curriculum Control Authority (CCA) TPP endorsement letter

A

Provides the approval to undertake the TPP.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

b. Cover page

A

Course title, cin, organization name and agency who prepares TPP, date, and security classification.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

c. Course data

A

Course title, cin, cdp, status-nem/revise/deactivation, mission statement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

d. Justification

A

benefits of the project with supporting documentation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

e. Safety Risks and Hazardous materials

A

state if course is high risk or not, any anticipated safety risks and exposures to hazmat.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

f. Curriculum development method

A

either task based curriculum development from navedtra 130 series or PPP/NTSP based according to 131 series.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

g. Resource requirements

A

manpower, equipment, materials, and funding.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

h. Compensation

A

state sources of compensation for all funding and manpower, where the money is coming from

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

i. Milestones

A

timeline of major development and implementation dates. When resources and materials will be procured and when proposals will become activated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Describe the web application SERENA.

A

It allolws LCs to upload, manage, and maintain TPPs from start to final approval

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Describe the type of TPPs housed in SERENA.

A

new, revised, modified and deactivated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Explain how TPPs are identified and maintained in SERENA

A

seperated by LC and given the next available number.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly