Before new equipment arrives at the plant for installing it are made by the
Plant engineer
When pouring a concrete footing, you should hold the steel rods in position with
tie wires
The best materials for filing around a foundation are gravel and
ground concrete slabs
The type of bolt to anchor the equipment is usually specified by the
equipment manufacturer
How long must new concrete sit before you can install equipment on it?
28 days
Retainers on the sides of horizontally reciprocating equipment keep it from
walking
To isolate anchor bolts when mounting equipment on pads, surround the bolts with
neoprene tubing
What type of wrench should you use for tightening anchor bolts
Torque
To drill anchor bolt holes larger than 1 1/2 in., you should use a
core bit with a diamond or carbon tip
You should not use a concrete mix to grout anchor bolts, because the concrete
shrinks when it sets
If new equipment is damaged in shipment you should report it to the
carrier
What must you do first before disconnecting the electrical wiring to existing equipment?
Shut off the power
What is the least number of rollers you should use under a load on a skid
Three
When moving equipment with a crowbar, what should you use between the bar and the floor?
A wood block
If you have no clearance to remove a sling after setting the equipment down, you should lower the equipment onto
wedges